Facts
The Federal Office of Transport (BAV) granted Swiss Federal Railways SBB AG (SBB AG) plan approval on 24 November 2015, subject to conditions, for the construction and operation of a railway radio installation at Tägerwilen-Gottlieben station. The installation comprises a new radio mast approximately 20 m high with two GSM-R antennas (130° and 280°) and a transmitter system in an existing technical building. The mast is planned in the eastern area of the station between the track installation and Konstanzerstrasse, on the railway-owned property No. 249 (land register of Tägerwilen).
[A. AG] (appellant 1), [B.] (appellant 2) and the Politische Gemeinde Tägerwilen (appellant municipality) filed objections during the project public display procedure. The BAV dismissed these, insofar as it did not enter into them or struck them off as moot. The objectors appealed the decision to the Federal Administrative Court, which joined the proceedings and dismissed the appeals by judgment of 7 February 2017 (A-227/2016).
Against this judgment, appellants 1 and 2 lodged a constitutional appeal with the Federal Supreme Court on 13 March 2017 (proceeding 1C_152/2017), and the municipality did so on 17 March 2017 (proceeding 1C_164/2017). They requested that the lower court's judgment be set aside and plan approval be refused, or in the alternative that the matter be remitted to the lower court. SBB AG and the BAV requested dismissal. The Federal Administrative Court waived a response, and the Federal Office for Spatial Development (ARE) waived comments. The Federal Office for the Environment (FOEN) considered the plan approval to be compliant with federal law. The reply briefs were filed; thereafter no one commented further on the matter. A request for suspension became moot through the lapse of time.
The Federal Supreme Court (I. Public Law Division) joined proceedings 1C_152/2017 and 1C_164/2017, entered into the appeals and dismissed them in their entirety.
Considerations
Admissibility: The constitutional appeal is available against the final decision of the Federal Administrative Court in a public law matter (Art. 82 lit. a, Art. 86 para. 1 lit. a, Art. 90 FSCA); no exclusion ground under Art. 83 FSCA applies. Appellants 1 and 2, as landowners within the perimeter in which the radiation still amounts to 10% of the installation limit value, have standing to appeal (Art. 89 para. 1 FSCA). The municipality has standing to appeal under Art. 89 para. 2 lit. d FSCA in conjunction with Art. 12 para. 1 lit. a NCHA to protect townscape and landscape conservation.
Phasing: Under Art. 18h para. 2 RailA, approval in stages is permissible insofar as the separate treatment does not prejudge the assessment of the overall project. A division may, however, contravene the requirement of material coordination (Art. 25a SPA) and the comprehensive weighing of interests if an overall assessment is necessary. The Federal Supreme Court considers the partial plan approval permissible in the result: the plan approval of an individual railway radio installation prejudges neither the site nor the design of further installations; an overall assessment with neighbouring sites must nevertheless be carried out, insofar as necessary, even for the individual approval. The location within the area of a line junction justifies the partial approval.
Incompleteness of the application: Under Art. 18b RailA, Art. 2a and 6 RailO and Art. 3 para. 2 lit. l and m PAPRO, safety assessment reports and expert review reports must in principle be submitted. The BAV guidelines (RL PAPRO, RL UP-EB), which, although they do not have the character of legislation, are professionally relevant, do not require independent review for telematics applications such as the GSM-R installation (Art. 38 RailO). It is therefore compatible with Art. 3 para. 2 lit. l and m PAPRO that the application was assessed without these reports. The approving authority nevertheless remains responsible for reviewing lawfulness. The question of when the ordinance provisions entered into force did not need to be resolved.
Clarification of facts and evidentiary requests: The lower court relied on information from the BAV dated 8 November 2016 and 18 November 2016, on the respondent's prediction maps and on an inspection in situ. The findings on the supply level (68 dBμV/m) and on the suitability of the site are sufficient and not manifestly incorrect. Since the BAV has expertise, the lower court was entitled to dispense with a court expert opinion. The failure to explain English technical terms does not violate the right to be heard. An inspection in situ before the Federal Supreme Court is not necessary.
Nature and heritage protection: The plan approval concerns a federal task (Art. 2 para. 1 lit. a NCHA), so Art. 3 and 6 NCHA must be observed. The site lies south of the ISOS object 'Schlosslandschaft Untersee' and the BLN object No. 1411 'Untersee-Hochrhein'; north of it is the ISOS object 'Gottlieben'. The lower court denied a significant impairment, since there is no unobstructed view from the installation of the protected town centre and the shoreline strip is partly built up. The Federal Supreme Court leaves open whether an interference exists at all: even if there were an interference, it would be merely minor, so the requirements of Art. 7 para. 2 NCHA for an assessment by the EKD and ENHK are not met. Minor interferences are permissible according to case law where a more significant interest justifies them (Art. 6 para.…