Facts

Parties and instances: The Federal Roads Office (ASTRA) invited tenders in October 2016 in an open procedure for a service contract (project 'Gesamtsystem Bypass Luzern', geology/geotechnics). The appellant is [A. AG] (the award recipient in the award decision of 21 February 2017). The respondent is the joint venture [B.] ([C. AG] , [D. AG] , [E. AG] ), which filed an appeal against the award with the Federal Administrative Court.

Tender and amendment of the documents: The tender was published on 18 October 2016 on SIMAP. The deadline for offers was 12 December 2016 (for previously involved bidders, 28 November 2016). On 19 October 2016 ASTRA informed all interested parties who had already downloaded the documents by e-mail of an adjusted 'fee calculation service table' that had to be mandatorily taken into account. The item 'Client fee reserve' was changed from a fixed amount of CHF 100'000.-- to 12% of the fee offer. Five offers were received within the deadline.

Course of proceedings: The award was opened on 21 February 2017. On 13 March 2017 the joint venture [B.] filed an appeal with the Federal Administrative Court, which ordered super-provisional measures prohibiting the implementation of the award. [A. AG] did not constitute itself as a party but reserved the right to appeal on 22 May 2017. By judgment of 27 September 2017 (B-1528/2017), the Federal Administrative Court upheld the appeal, annulled the award, excluded the offer of [A. AG] and newly awarded the contract to the joint venture [B.] .

Requests before the Federal Supreme Court: By appeal of 1 November 2017, [A. AG] requested that the judgment of the lower instance be set aside; in the alternative, that the proceedings be discontinued by reformatory upholding of the appeal; in the further alternative, that the matter be remitted to ASTRA. No responses were obtained.

Core questions of the appellant: (1) Violation of transparency, equal treatment, the prohibition of discrimination, Art. IX para. 10 GPA, the prohibition on amending the tender documents and the investigative principle (Art. 12 APA) through a reformatory decision after a material amendment of the documents without the consent of all bidders; (2) violation of the duty of good faith and the principle of transparency through the lack of notice of the extension of res judicata to the award recipient upon joinder, without consequence; (3) violation of transparency and equal treatment through the exclusion, ordered ex officio, without prior hearing of the award recipient and the contracting authority.

Considerations

Admissibility (Art. 83 let. f FSCA): The Federal Supreme Court examines the admissibility requirements ex officio (Art. 29 para. 1 FSCA) with free review (Art. 95 FSCA). The subject matter is the award of a contract that is subject to the Federal Act on Public Procurement (PPA) (Art. 2 para. 1 let. a PPA). A decision of the Federal Administrative Court in the area of public procurement is admissible under Art. 83 let. f FSCA only if the contract value reaches the threshold or a question of law of fundamental importance arises (Art. 83 let. f no. 2 FSCA). The legal question must be of procurement law nature, guiding for practice and material to the specific case; the mere novelty of the question or the application of existing principles to an individual case is not sufficient. The appellant must set out the requirement (Art. 42 para. 2 FSCA).

First question (amendment of the tender documents): The appellant registered only after the amendment and downloaded the documents on 24 October 2016; the adjusted and the original table were available to it at the same time (binding factual findings, Art. 105 para. 1 FSCA). The amendment was therefore not suitable to materially impair its claim to equal treatment, and it was not aggrieved by the amendment. The question is therefore not decisive for the outcome. As to the principle of transparency and the investigative principle, there is no need for clarification: according to case law, interested parties may expect, in the case of contradictory documents, that they inquire promptly with the contracting authority (good faith, Art. 5 para. 3 Cst.). The investigative principle (Art. 28 para. 1 PPA, Art.…