Facts
Parties and instances: Appellant 1 (a public limited company) and appellant 2 (a natural person), as well as the political municipality of Tägerwilen as appellant, lodge a complaint in public law matters against the judgment of the Federal Administrative Court, Division I, of 7 February 2017 (A-227/2016). The respondent is Schweizerische Bundesbahnen SBB AG (Infrastructure). The Federal Office of Transport (BAV) is involved as the approval authority. The Federal Supreme Court (First Public Law Division) has joined proceedings 1C_152/2017 and 1C_164/2017.
Subject matter: Plan approval for a GSM-R railway radio installation at the Tägerwilen-Gottlieben site.
Facts:
- On 24 November 2015 the BAV granted SBB AG, subject to conditions, the plan approval for the construction and operation of a railway radio installation. It comprises a new radio mast of approximately 20 m height with two GSM-R antennas (130° and 280°) and a transmission installation in an existing technical building. The mast is planned on railway-owned plot No. 249 in the eastern station area between the track system and Konstanzerstrasse.
- Appellants 1 and 2 and the municipality had raised objections in the public display procedure; the BAV dismissed them insofar as it did not strike them from the record.
- The Federal Administrative Court dismissed the joined appeals by judgment of 7 February 2017.
- Appellants 1 and 2 lodged an appeal with the Federal Supreme Court on 13 March 2017, and the municipality on 17 March 2017. They requested that the judgment be set aside and the plan approval be refused, or alternatively that the matter be remitted to the lower court.
- SBB AG and the BAV requested dismissal. The FOEN considered the plan approval to be compliant with federal law, and the ARE waived comments.
- A request for suspension until the end of June 2018 became moot through the passage of time.
Considerations
Admissibility: The contested decision is a final decision of the Federal Administrative Court in a public law matter (Art. 82 lit. a, Art. 86 para. 1 lit. a, Art. 90 FSCA); no exclusion ground under Art. 83 FSCA applies. Appellants 1 and 2, as property owners within the perimeter where radiation still amounts to 10% of the installation limit value, have standing to appeal (Art. 89 para. 1 FSCA). The municipality is entitled to appeal in nature and heritage protection matters on the basis of Art. 89 para. 2 lit. d FSCA in conjunction with Art. 12 para. 1 lit. a NCHA. The appeals are admissible. The complaint of violation of federal law is examined under Art. 95 lit. a FSCA, and the facts under Art. 105 FSCA.
Phasing (Art. 18h para. 2 RailA): The municipality complained that the partial plan approval constituted an impermissible phasing of the line project. The Federal Supreme Court holds that phases are permissible where separate treatment does not prejudge the assessment of the overall project; even where division is permissible, however, the cumulative effects must be examined (Art. 25a SPA). The lower court justified the partial approval on the ground that the installation lies in the junction area of the Schaffhausen-Kreuzlingen and Weinfelden-Kreuzlingen lines. This is not objectionable in its result. A single base station does not prejudge the location or design of further installations; however, an overall view in relation to neighbouring sites must, to the extent necessary, also be taken when approving an individual installation.
Incompleteness of the application (Art. 18b RailA, Art. 3 NCHA): The absence of safety assessment reports (Art. 3 para. 2 lit. l PAPRO) and of expert review reports (lit. m) was complained of. The BAV may review documents itself or have them reviewed by experts (Art. 2a and Art. 6 para. 3 RailO). The BAV's guidelines (RL PAPRO, RL UP-EB) are not statutory, but are relevant as an expression of technical expertise. Under these guidelines, no independent review is required for telematics applications (here GSM-R, a telematics application within the meaning of Art. 38 RailO). The absence of the reports is therefore consistent with Art. 3 para. 2 lit. l and m PAPRO. Whether the provisions were already in force at the time the application was filed need not be examined.
Establishment of facts and expert opinion: The lower court relied on information provided by the BAV on 8 November 2016 and 18 November 2016, as well as on prediction maps and an on-site inspection. The BAV has specialist expertise, so the lower court was entitled to dispense with a court-appointed expert opinion. The use of untranslated English technical terms does not violate the right to be heard. An on-site inspection in the proceedings before the Federal Supreme Court is not necessary.
Nature and heritage protection (Art. 3 and Art. 6 NCHA, Art. 17 RailA): The plan approval fulfils a federal task (Art. 2 para. 1 lit. a NCHA). The site lies immediately south of the ISOS object 'Schlosslandschaft Untersee' and the BLN object No. 1411 'Untersee-Hochrhein'. The lower court found no significant impairment. The Federal Supreme Court leaves open whether there is an intervention at all; even if affirmed, it would be merely minor in its distant effect, so that no expert assessment by the EKD or ENHK under Art. 7 para. 2 NCHA is required.…