Facts
Following the introduction of the so-called 'East approaches' on runway 28 of Zurich Airport in October 2001, numerous landowners from the affected region requested compensation from Flughafen Zürich AG for the diminution in value that had occurred. The Municipality of Kloten as well as several natural and legal persons (the expropriated parties) were affected, whose plots are directly overflown during approach.
The Federal Assessment Commission, District 10 (ESchK) in eight decisions of November and December 2011 rejected the claim of [B. AG] and partially upheld the remaining claims. It calculated the diminution in value only for the perpendicularly overflown part of the property, for single-family houses according to the MIFLU I model and for income-producing properties according to the ESchK hedonic model, made equitable deductions, and set a surcharge for noise-independent aspects of direct overflight.
Against the assessment decisions, the expropriated parties as well as Flughafen Zürich AG and the Canton of Zurich (the expropriators) filed appeals with the Federal Administrative Court, which on 1 April 2014 partially upheld the appeals, partially set aside the decisions and remanded the matter to the ESchK for reassessment. The Federal Administrative Court decided in particular that the diminution in value of the entire property was to be compensated, that the ESchK hedonic model for income-producing properties in Kloten was not applicable and had to be replaced by a grid, and that the surcharge was to be set as a percentage of the market value without aircraft noise.
The expropriators filed appeals against the eight decisions of the Federal Administrative Court with the Federal Supreme Court in public law matters and requested the reduction of the compensation or the award of no compensation. The Federal Supreme Court partially upheld the appeals at its public session of 17 March 2016 and dismissed them in all other respects. It set aside the contested decisions and remanded the matter for new adjudication to the Federal Administrative Court, which is to rule definitively, if possible without remand to the ESchK.
Considerations
The Federal Supreme Court distinguishes between expropriation of neighbourly defensive rights against excessive immissions and expropriation through direct overflight. A direct overflight exists where the airspace attributable to landownership under Art. 667 para. 1 CC is directly infringed, the aircraft regularly penetrating the air column at low altitude. In place of the action under Art. 641 para. 2 CC, the claim to expropriation compensation arises, comparable to a compulsory overflight easement. It was undisputed that the requirements of direct overflight were met; the amount of compensation was contested.
On the extent of compensation, the Federal Supreme Court maintains its practice whereby the owner of a directly overflown plot is also compensated for the aircraft-noise-related diminution in value, regardless of the foreseeability of the immissions. The change of practice sought by the expropriators would merely create new inequalities, for example in relation to owners in the Canton of Geneva who had already been fully compensated. The existing practice was understood as judicial gap-filling under Art. 1 para. 2 CC, which is to be maintained for reasons of legal certainty and equality before the law, as long as the legislator does not regulate otherwise.
In principle, the diminution in value of the entire property is to be compensated (Art. 16 and Art. 19 lit. b ExprA), even where only a marginal area, for example with a wing, penetrates the air column. Special features such as overflight of only a marginal area or unusual plot sizes may however be taken into account in the assessment. For unusually large plots and/or plots built over with several houses, of which only a small part is overflown, the practice may lead to objectionable results. A conceptual division of the plot into hypothetical plots is then appropriate. For plot No. 4290 of B. AG (11'084 m2, nine multi-family houses, only 1'299 m2 and two houses overflown), it is inequitable to compensate all houses; compensation is limited to the overflown buildings together with their surroundings (approximately two-ninths). The same applies to plot No. 3465 of the Municipality of Kloten. For the undeveloped plot No. 4962 of A. (3'479 m2, only 7.8% overflown), limitation to the overflown part is justified, since development with several houses is imposed.
For calculating the diminution in value for income-producing properties in Kloten with evening and night-time East approaches, the Federal Supreme Court holds that the ESchK hedonic model rests on extensive transaction data, is statistically plausible and reliable, and permits a schematic assessment. The minor effects of the East approaches on diminution in value do cast doubt on its applicability, but the MIFLU I model, which was developed for owner-occupied single-family houses, cannot readily be transferred to income-producing properties without further investigation. Whether one or both models require correction can only be assessed with…