Facts

Die Swissgrid AG operates the Swiss transmission grid. The Rheinkraftwerk Säckingen AG (registered office in Bad Säckingen, Germany, service address in Stein AG, rated capacity 74 MW) and the Kraftwerk Ryburg-Schwörstadt AG (registered office in Rheinfelden, rated capacity 120 MW) operate hydropower plants on the Rhine at the national border. The energy generated is fed via one connection each into the German and the Swiss distribution grid (grid level 3).

On 29 April 2014 the Federal Electricity Commission ElCom ordered Swissgrid not to grant, from 1 June 2014 onwards, the capacity priority previously granted in the cross-border transmission grid. The power plants thereupon applied on 27 June 2014 for priority under Art. 17 para. 2 ESA for their entire production (Säckingen: currently 27.5 MW per direction plus 8 MW compensation for impoundment to Laufenburg; Ryburg-Schwörstadt: 30 MW plus 15 MW for generator 3, depending on the direction). The German transmission system operators terminated the previous cooperation agreement effective 31 December 2014; from 1 January 2015 a new agreement applies without a priority rule. By submissions of 2 March 2015 the power plants additionally requested a declaration that the agreement is void, the conclusion of a cooperation agreement compliant with national law, and the payment of the auction proceeds from 1 January 2015.

By decisions of 19 May 2015 ElCom dismissed the applications: Art. 17 para. 2 ESA was not applicable, as there was no cross-border supply via the transmission grid, but the electricity was fed directly into the respective national distribution grids.

The Federal Administrative Court (Division I) partially upheld the appeals of the power plants by two largely identically worded judgments of 22 March 2016 (A-4025/2015 and A-4043/2015), set aside the decisions and remanded the matter to ElCom for the granting of priority and for the examination of a claim for reimbursement. The court costs of Fr. 15'000.- were imposed on Swissgrid, which had to pay the power plants a party compensation of Fr. 10'000.-. The court did not enter into the requests concerning instructions for negotiation to Swissgrid and the declaration of nullity of the cooperation agreement.

On 3 May 2016 Swissgrid filed public law appeals with the Federal Supreme Court (2C_390/2016 and 2C_391/2016) and requested the annulment of the judgments of the Federal Administrative Court and the confirmation of the ElCom decisions. ElCom requested that the appeals be upheld; the power plants requested that they be dismissed. The Federal Administrative Court waived a response. DETEC expressed its views without making an application. The proceedings were joined on 4 April 2017; on 2 May 2017 a preparatory hearing took place. On 17 March 2017 the Federal Assembly adopted an amendment to the ESA (in force since 1 October 2017), which restricts Art. 17 para. 2 and contains a transitional provision in Art. 33b.

Considerations

Admissibility: The contested decisions are remand decisions and therefore interlocutory decisions, which are appealable under Art. 93 para. 1 let. b FSCA, since the investigations ordered entail considerable effort that could be avoided if the appeal were upheld. Swissgrid, as transmission system operator, has standing to appeal (Art. 89 para. 1 FSCA). In the event of remand, the unsuccessful party may state its requests in its response; the Federal Supreme Court may make concrete statements on the implementation of the priority right (Art. 93 para. 3 FSCA).

Applicable law and subject matter of the dispute: The new law (revArt. 17 para. 2 ESA) is not applicable; the applications were submitted under the previous law, and under Art. 33b ESA a priority applies until 30 September 2018 at the latest. The subject matter of the dispute was restricted in the course of the proceedings to the priority return transport of that electricity which, as a result of asymmetric feed-in, exceeds the 50% distribution key, and is therefore limited to this question.

Wording of Art. 17 para. 2 ESA: The wording does not require that the party entitled to priority be directly connected to the cross-border transmission grid or depend on it. All producers and distribution system operators may use the cross-border transmission grid on the basis of network access (Art. 13 ESA). A priority that applies only where technically and operationally necessary cannot be derived from the law; to that extent the Federal Supreme Court agrees with the power plants and the lower court.

Criticism of the lower court: The lower court relies on the wording but at the same time qualifies the priority (no maximisation, no undue arbitrage gains, regard for equal treatment). This view is contradictory. Exploiting economic advantages arising from the priority is the inherent purpose of a promotional measure and is therefore not abusive. The lower court also left the essential legal questions open and thereby created no legal certainty, although the Federal Administrative Court would have to issue binding instructions in the case of remand (Art. 61 para. 1 APA).

Systematic, historical and teleological interpretation: Systematically, Art. 17 para. 2 ESA is an exception to market-oriented capacity allocation (Art. 17 para. 1 ESA); priority rules require justification and, in case of doubt, are to be interpreted narrowly; there is also a connection to Art. 13 of the 1972 EEC-Switzerland Agreement. The legislative history shows only the general aim of promoting renewable energy, but not the concrete scope of the priority. The border power plants were not separately privileged under the previous law; their electricity, as hydropower, is in any case prioritised under Art. 13 para. 3 let. c ESA. The practical circumstances (limited capacity) do not lead to an interpretation deviating from the wording, since the capacity was previously sufficient for the priorities asserted and other priorities practically cannot be asserted.

Result on priority: The priority is…