Facts

The dispute concerns a total construction contract for the construction of a villa (villa B) within the real estate project "[D.] " in Versoix (GE). The architect (appellant, plaintiff at first instance) designed the project in 2002-2003 and entered into a simple partnership in 2004 with a civil engineer and an administrator of the construction company [E. SA] . This agreement provided that the earthworks, concrete and masonry would be entrusted to [E. SA] and that the architect and the administrator would each purchase a villa at cost price.

Spouses [B.B.] and [C.B.] (respondents, defendants at first instance) acquired the plot for villa B for 501'500 fr. A document from June 2004 entitled "Détail du prix de vente de la villa B" indicated a lump-sum price including VAT of 1'360'000 fr., of which 858'500 fr. was for construction, and an estimate of the works of 860'000 fr. The sale of the plot was conditional on the signing of an architect's mandate covering the construction at a global price of 858'500 fr.

Construction began in December 2004 and was completed in early 2006. The architect invoiced the spouses for the actual amount of the contractors' invoices, or the lower estimated amount where the invoice was smaller. A summary list showed a total cost of 792'492 fr.90, and the spouses paid instalments of 767'242 fr.90. A provisional acceptance report was signed on 27 January 2006. A provisional final statement of account dated 30 April 2007 showed additional works (extra work) of 158'600 fr. incl. VAT, without detail by contractor.

Relations deteriorated from November 2006. [E. SA] sued the architect for payment, and the Federal Supreme Court, in judgment 4A_471/2010, classified the relationship between the spouses and the architect as a contract for work within the meaning of art. 363 CO.

On 15 March 2013, the architect served the spouses with a payment order for 249'856 fr.10, which was contested. He brought an action on 20 August 2013 before the Geneva Court of First Instance, which dismissed him in full on 21 December 2015. On appeal, the architect sought only 219'157 fr.10 with interest. The Civil Division of the Geneva Court of Justice dismissed the appeal on 23 September 2016, holding that the parties had a common and real intention to fix the price according to the value of the actual work (art. 374 CO), with a mere maximum price of 858'500 fr. for the construction. It also held that the architect had not proven the extra work, for lack of invoices.

The architect appeals to the Federal Supreme Court and principally seeks payment of 219'157 fr.10 with interest at 5% from 27 January 2006, with definitive discharge of the attachment, and subsidiarily remittal of the case to the cantonal court.

Considerations

The appeal is admissible under arts. 72, 74 para. 1 let. b, 75, 76 para. 1, 90 and 100 FSCA, the amount in dispute exceeding 30'000 fr. The Federal Supreme Court rules on the basis of the facts established (art. 105 para. 1 FSCA) and may correct them only if they are manifestly inaccurate, i.e. arbitrary, and if the correction is capable of affecting the outcome of the case (art. 97 para. 1 FSCA). A challenge to the facts is subject to the strict requirement of substantiation (art. 106 para. 2 FSCA).

It is not disputed that the contract is a total construction contract subject to arts. 363 et seq. CO. The dispute concerns whether the price was agreed as a lump sum (art. 373 CO) or according to the value of the work (art. 374 CO), with a mere maximum price. The first ground alleges a violation of art. 18 para. 1 CO and of the principle of trust, reproaching the cantonal court for having disregarded six items of evidence which would establish a lump-sum price of 1'360'000 fr.

The Federal Supreme Court finds that the cantonal court was able to establish the parties' real intention through a subjective interpretation, on the basis of assessed evidence. There is therefore no room for normative interpretation according to the principle of trust. Only a review for arbitrariness would be possible, yet the appellant does not substantiate any arbitrariness complaint meeting the requirement of substantiation. His criticisms are appellate in nature and therefore inadmissible.

The second ground…