Facts

[C. AG] (contractor, plaintiff, respondent), as general contractor, concluded on 18 December 2006 a partial general contractor works contract with the building owners [A.A.] and [B.A.] (defendants, appellants) concerning a residential and commercial building in [U.] at a lump sum of CHF 895'000.--. The SIA Standard 118 (1977/1991 edition) was decisive, with Art. 363 et seq. CO applying subsidiarily.

By final invoice of 14 November 2008, the contractor claimed CHF 404'313.80 (CHF 162'250.-- outstanding payment and CHF 242'063.80 additional/reduced costs, of which CHF 18'984.-- interest costs). The building owners paid CHF 75'000.-- on 24 December 2008.

The Rheintal District Court (action of 20 July 2009) and subsequently the Regional Court initially awarded the plaintiff CHF 112'284.75. The St. Gallen Cantonal Court (III Civil Chamber), by judgment of 17 February 2015, partially upheld the plaintiff's appeal and ordered the defendants to pay CHF 245'239.85 plus 5% interest since 24 December 2008; it dismissed the action for the remainder.

The building owners lodged a civil law appeal with the Federal Supreme Court and requested annulment and dismissal of the action, or alternatively remittal. The opposing party requested dismissal of the appeal. The lower court waived a response. An application for suspensive effect was dismissed.

The disputed items included in particular: additional reinforcement costs, excavation of the building pit, lift pit, external drainage, utility lines, municipal excavation, carpentry and additional works, [G.] artificial stone elements, interest costs, as well as counterclaims for the missing screed floor and missing screed staircase.

Considerations

The Federal Supreme Court examines questions of law ex officio (Art. 106 para. 1 FSCA), but in principle only addresses sufficiently substantiated complaints (Art. 42 para. 2 FSCA). It is bound by the findings of fact only if they are manifestly incorrect (arbitrary) and remedying the defect is decisive (Art. 105 para. 2, 97 para. 1 FSCA). An assessment of evidence may be corrected only if it is arbitrary.

The right to be heard was not violated: the unconditional right to reply does not relieve a party of the obligation to set out procedurally adequately which submissions are new. The duty to give reasons is also satisfied if the decision can be challenged in a meaningful way; an express engagement with every argument is not required.

A lump-sum price under Art. 41 in conjunction with Art. 40 SIA 118 is a fixed undertaking (Art. 373 CO, Art. 38 SIA 118). Under special circumstances, however, there is still an entitlement to additional remuneration; under Art. 58 para. 2 SIA 118 where the building owner is at fault, measured according to Art. 86-91 SIA 118. A change of order is not necessarily required for this.

Regarding the reinforcement (additional costs of CHF 49'558.70, awarded by half): the error in the engineer's estimate engaged by the building owners is a lack of care on the part of an auxiliary person (Art. 101 CO) and constitutes fault. The contractor was entitled to rely on expert information, unless the incorrectness was obvious or recognisable upon verification. The duty to warn under Art. 25 SIA 118 applies only from the conclusion of the contract and concerns the formation of consensus on the lump-sum price. The lower court found that the error was recognisable before the contract was concluded, but not that it was obvious; the appellants did not substantiate this, so the contractor's basis of claim remained. The contractor did not appeal the half that was attributed to it.

Regarding the building pit excavation (division two-thirds/one-third): the assessment of evidence is based on the statements of the contractor's project manager and the architect. The fact that the witness is a senior employee does not make his statement arbitrary. A complaint against the division under Art. 25 para. 1 SIA 118 or Art. 89 SIA 118 was not sufficiently substantiated.

Regarding the lift pit: the assessment of evidence (meeting minutes, witness statement) is not arbitrary. A duty to warn, raised for the first time before the Federal Supreme Court, is irrelevant, since nothing was submitted on this before the lower court and no findings were made.

Regarding the external drainage (division by half): the lower court wrongly applied Art. 99 para. 3 in conjunction with Art. 44 CO as a rule on damages. Since the matter concerns an adjustment of the fixed price and not damages, within the scope of SIA 118 Art. 44 CO nevertheless applies by analogy, because the SIA Standard (Art. 166, 169, 170 SIA 118) provides for a graduated consideration of partial causes. The discretionary decision is not manifestly unreasonable and stands.

Regarding the utility lines (CHF 3'168.70): if the contractor claims additional remuneration beyond the lump-sum price, it bears the burden of proof under Art. 8 CC that the lump-sum price did not include these expenses. This proof was lacking; the item is to be dismissed.

Regarding the municipal excavation: the appellants' denial was insufficient, since the point was left open and not disputed. The claim is well founded, as the building owners' incorrect information was causal.

Regarding the carpentry and additional works: the interpretation of the contract is primarily based on the common actual intention (assessment of evidence), and subsidiarily on the principle of trust at the time of conclusion of the contract. The lower court did not find a common intention and interpreted the contract according to the principle of trust. The contract wording 'Carpentry works; roof structure with roof insulation incl. internal and external timber cladding' and the information on the estimate indicate that the panelled ceilings (BKP 283.4) were included in the lump-sum price. The action is therefore to be dismissed as regards CHF 40'869.45. The Fermacell knee walls and the taping of windows…