Facts

The dispute opposes a public limited company that owns a plot of land (the appellant, appellant before the cantonal court) to an architect operating a workshop as a sole proprietorship (the respondent). Subject matter: architect's contract.

On 14 November 2013, the parties concluded an architect's contract for the design and construction of a high-end chalet. Art. 5 of the contract provided for fixed fees calculated on the basis of the summary cost estimate of the project annexed to it. Art. 6 set the amount of fees and expenses at CHF 756,000, as an overall and inclusive fixed price. The initial estimate of the construction cost amounted to CHF 19,061,234.

The final fee note of 5 January 2017 amounted to CHF 756,000 and contained a heading 'settlement of all accounts'. The architect claimed the balance of CHF 80,000, then thanked the client after receiving the full contractual payment and the final balance, specifying that this amount was paid as payment of the final note.

On 18 August 2017, the architect sent the company a statement of the additional hours actually worked within his workshop, representing an added value of CHF 217,298.50. The company did not respond.

By claim of 18 November 2019, the architect claimed CHF 260,820 with interest at 5% from 5 July 2019. A judicial expert review was entrusted to an architect. The expert confirmed that the increase in the construction cost, which rose to CHF 25,639,865 because of project modifications made during construction, masonry work, joinery, technical installations, operating equipment, external works, miscellaneous and unforeseen items, and finishing work (some of which gave rise to additional public notices of planning applications), entailed an increase in fees. The additional cost of CHF 260,820 corresponded to services for additional public notices of planning applications, for modifications made without public notice, and to ordinary services of study, coordination and execution of the works over two and a half years.

By judgment of 12 June 2023, the Cantonal Chamber for Property Matters of the Canton of Vaud ordered the company to pay CHF 260,820 with interest at 5% from 5 July 2019. By decision of 11 July 2024, the Civil Court of Appeal of the Cantonal Court of the Canton of Vaud dismissed the appeal and confirmed the judgment.

The company lodges a civil law appeal with the Federal Supreme Court, seeking mainly the annulment of the decision and, in the alternative, its reform so that it owes no sum. It requested suspensive effect, which was refused by order of 4 October 2024. The respondent seeks dismissal of the appeal.

Considerations

As to admissibility, the appeal is directed against a final decision (Art. 90 FSCA) rendered in civil matters (Art. 72 FSCA) by a higher court ruling on appeal (Art. 75 FSCA), the amount in dispute of CHF 30,000 being met (Art. 74 para. 1 let. b FSCA). The appeal is in principle admissible. The Federal Supreme Court applies the law of its own motion (Art. 106 para. 1 FSCA) but, given the duty to state reasons (Art. 42 para. 2 FSCA), only examines the grounds raised, and may revisit the facts found only if they are manifestly inaccurate (arbitrary) and the correction is likely to affect the outcome of the case (Art. 105 para. 2, 97 para. 1 FSCA), in accordance with the strict principle of pleading (Art. 106 para. 2 FSCA). Arguments aimed at re-arguing the merits are inadmissible.

The complaint alleging a violation of Art. 312 para. 1 CPC and of the right to be heard (Art. 29 para. 2 Cst.) is inadmissible for lack of a legitimate interest: the appellant was the party appealing, only the respondent could have had an interest in responding, and he suffered no prejudice from the dismissal of the appeal.

As to the violation of Arts. 8 CC, 55 para. 1, 152, 157 and 316 CPC and of the principle of equality, the appeal is largely a re-argument on the merits and therefore inadmissible. The cantonal court considered the expert report complete, noting that the expert had ventured into some legal aspects without this detracting from the value of his report. The complaint seeking a supplementary expert opinion is not substantiated. The complaint based on the impossibility of responding to documents handed to the expert does not appear in the contested decision and was not raised on appeal: it is inadmissible for failure to exhaust the cantonal remedies. The appellant also invoked the receipt for settlement of all accounts (exhibits 100 to 103) and Arts. 18 and 88 CO; the cantonal court took them into account, the question being that of their scope.

On the merits, the contract is mixed (planning and direction of works), subject to the rules of mandate or of contract for work according to the services provided (ATF 134 III 361). Art. 373 CO applies where remuneration is fixed: the contractor cannot claim an increase even if the work required more effort, except in case of a change in the order, which permits an increase in remuneration under Art. 374 CO. It is for the contractor to prove the change in the order and the additional costs resulting from it.

The cantonal court held that the fixed price had been set on the basis of the cost of the project, as the expert had confirmed. As to the interpretation of intent, the judge first seeks the real and common intention of the…