Facts

This case involves a dispute between property owner [A.] and the City of Zurich regarding the relocation of a pedestrian and vehicular right-of-way. [A.] is the owner of the property with Cadastre No. s on B. Street t in U. The property includes a strip of land at the rear of the house that can be used as a parking area. The adjacent property to the north, Cadastre No. u, C. Street v, belongs to the City of Zurich.

Access to the rear of A.'s house is secured by a pedestrian and vehicular right-of-way according to Servitude Protocol w. This right-of-way runs diagonally from C. Street across property u and then continues towards property s. The City of Zurich plans to grant a building right on its property u and replace the existing house on C. Street v with a new building. A building passage with a clear height of 3.6 meters is planned.

The City of Zurich filed a lawsuit demanding the modification of the servitude w in the sense that the area be relocated and the pedestrian and vehicular right-of-way in the future lead through an opening in the new building towards C. Street. [A.] unsuccessfully challenged the building permit for the construction project and now appeals to the Federal Supreme Court to dismiss the lawsuit.

Considerations

The Federal Supreme Court examines whether the claimed relocation of the right-of-way due to the disputed restriction of the passage height to 3.6 meters is not less suitable for the beneficiary within the meaning of Art. 742 para. 1 of the Swiss Civil Code (ZGB). It clarifies that in assessing the suitability of the new place of exercise, not only the horizontal but also the vertical dimension must be taken into account.

The decisive factor is whether the new place of exercise is…