Facts

On 10 October 2014, the Department of Planning, Housing and Energy of the Republic and Canton of Geneva granted [C.] and [B.] a preliminary building permit for five high-energy-performance villas, in contiguous order, on plots no. 4'307 and 4'175 in the municipality of Plan-les-Ouates.

By judgment of 29 June 2016, the Court of First Instance confirmed this decision on the appeal of [A.] , [D.] and [E.] .

By decision of 12 September 2017 (ATA/1273/2017), the Administrative Chamber of the Geneva Court of Justice dismissed the appeal lodged by [A.] and [D.] .

[A.] , represented by counsel, lodges a public law appeal with the Federal Supreme Court. He seeks annulment of the cantonal decision and of the preliminary building permit, or in the alternative, referral of the matter back to the Administrative Chamber for a new decision. No exchange of written submissions was ordered.

Subject matter of the dispute: preliminary building permit.

Considerations

The Federal Supreme Court first examines its jurisdiction. The appeal is in principle admissible as a public law appeal (art. 82 ff. FSCA) against a decision of last cantonal instance in matters of spatial planning and construction, no exception under art. 83 FSCA being applicable.

A preliminary building permit within the meaning of art. 5 para. 1 LCI constitutes a mere step towards the definitive permit and has an incidental character, even where the cantonal authority definitively decides certain elements that are determinative for the project. Such a decision may therefore be subject to immediate appeal only if it satisfies the requirements of art. 93 para. 1 FSCA.

As a general rule, the grant of a preliminary permit does not cause irreparable harm to objectors, since it only allows the beneficiary to take the steps necessary to obtain the definitive permit. Objectors may subsequently appeal against the definitive permit and against the interlocutory decision. The Federal Supreme Court exceptionally accepts irreparable harm where the disputed question is of fundamental importance and the project would have to be substantially reworked if the appeal were upheld, in order to guarantee legal certainty and transparency. This exception does not apply if an early examination would contravene the principle of coordination (art. 25a Cst.) or if the parties can reasonably await the final decision. The right to a reasonable time limit (art. 29 para. 1 Cst.) may also exceptionally justify entering into the merits.

In the present case, the appellant does not demonstrate…