Facts

The Federal Office of Transport (BAV) granted Swiss Federal Railways SBB AG (SBB) plan approval on 17 August 2015, subject to conditions and reservations, for the railway project 'Infrastrukturmassnahmen Zugersee Ost' (Infrastructure measures Zugersee Ost). The project comprises four sub-projects: TP 1 Double track Walchwil, TP 2 Preservation of substance of the Zug-Arth-Goldau tunnel, TP 3 Preservation of substance of the Zug-Arth-Goldau structures/track, and TP 4 Safety measures against natural hazards Zug-Arth-Goldau.

The interest group (IG) Neat Zug filed an objection, which the BAV essentially rejected; it did not enter into the expropriation compensation claim. The Federal Administrative Court dismissed the appeal of IG Neat Zug by judgment of 10 January 2017 (A-6015/2015), insofar as it was admissible. IG Neat Zug filed a public law appeal against this judgment with the Federal Supreme Court, requesting the annulment and refusal of plan approval, or alternatively remittal to the lower court. SBB and the BAV requested dismissal; the Federal Office for the Environment (BAFU) considered the plan approval compliant with environmental law. The President of the First Public Law Division granted suspensive effect to the appeal on 14 March 2017.

IG Neat Zug opposed only TP 1 (Double track Walchwil). In particular, it complained of the lack of a planning basis and a formal defect in the cantonal sectoral plan, the necessity and cost-effectiveness of the project, and the examination of variants (variant 'Murpfli'), the excessive noise burden from rail operations, the limit values of the Noise Abatement Ordinance (NAO), the traffic forecast, the noise calculation using the models SEMIBEL and sonRAIL, curve squeal, and the lack of precautionary noise protection measures. In the proceedings it filed requests for access to the files (granted by the Federal Supreme Court on 27 December 2017, inspection on 23 March 2018) and, after inspection of the files, repeatedly supplemented its submissions and alternative requests.

Considerations

Admissibility: The appeal is directed against a final decision of the Federal Administrative Court in a public law matter (Art. 82 lit. a, Art. 86 para. 1 lit. a and Art. 90 FSCA). IG Neat Zug, as an association protecting the interests of its members, has standing; the requirements for egoistic association appeals are met (BGE 142 II 80 consid. 1.4.2). New legal complaints are admissible within the scope of Art. 99 FSCA, but complaints raised belatedly under Art. 42 para. 1 in conjunction with Art. 100 FSCA are not. Alternative requests that merely specify the request for remittal are admissible.

Procedural complaints: There was no right of access to the files before the lower court, since IG Neat Zug did not request inspection of the lower court's files with its request of 4 December 2016. The defect was not cured by the inspection of the files at the Federal Supreme Court. The request for an oral hearing was rightly rejected as belated and dilatory. There is no violation of fairness, impartiality (Art. 29 para. 1 Cst., Art. 6 no. 1 ECHR) or Art. 30 Cst.

Planning basis: TP 1 gives concrete form to the capacity expansion under Art. 4 lit. a no. 4 FDRIA. The open alignment corresponds to the cost framework of the FinöV Dispatch. The cantonal sectoral plan amendment was approved by the DETEC on 11 November 2013, so there is no formal defect. The complaint regarding the Sectoral Plan Transport was raised belatedly and need not be examined.

Examination of variants and necessity: The authority must examine variants that are seriously under consideration; the Federal Supreme Court only reviews conformity with federal law, not whether the variant is the best one. Art. 9 FDRIA in conjunction with Art. 18b RailA does not require a comprehensive cost-effectiveness review; the variant study was known to the appellant, and anticipatory assessment of evidence is permissible. The necessity of the project was rightly affirmed; the Rotkreuz link and variant 'Murpfli' (with significant operational disadvantages) could be discarded. Belated complaints regarding freight transport, Art. 170 Cst. and Art. 8 Cst. are excluded.

Noise law classification: This is not a noise remediation; the EPA and the NAO are decisive. The project is a modification of an existing installation. No disproportionate extension and no modification comparable to new construction. Based on the overall assessment (capacity expansion and long extension of service life through preservation of substance), the modification is considered significant (Art. 8 paras. 2 and 3 NAO), so the immission limit values (IGW) must be complied with.

Exposure limit values: The IGW of the NAO, the formation of the average level, the rail bonus (K1) and the absence of a maximum level criterion are compliant with federal law. The preparatory work for reviewing the limit values is delayed, but does not justify a stay of proceedings. The interim target of the WHO night noise guidelines (55 dB(A)) supports the comparability with the IGW system. The question of the rail…