Facts

Parties and courts: The owners (the principals, defendants and appellants) entrusted an architectural firm (public limited company, plaintiff and respondent) with the renovation of a 167 m2 house on a 2'557 m2 plot located in the canton of Vaud. The dispute concerns the balance of the architect's fees and his liability for a cost overrun. The Civil Court of the Vaud Cantonal Court issued a judgment on 6 October 2016, confirmed by the Civil Court of Appeal on 4 July 2017. The principals brought an appeal in civil matters before the Federal Supreme Court on 11 September 2017.

Contract and estimate: A first project dated 30 January 2008, with an extension and a swimming pool (1'584'183 fr. 51), was rejected by the principals in April 2008 because the cost was too high. An estimate dated 18 April 2008, corrected on 22 April 2008, put the works at 812'784 fr. 97, fees included (120'176 fr. 82). No written contract was concluded and SIA Standard 102 was not declared applicable. The works began in May 2008 and ended at the end of December 2008.

Overrun: From 30 July 2008, the estimate was exceeded by approximately 100'000 fr., in particular because of an error in estimating the masonry item (38'800 fr. estimated, finally 149'500 fr.). The principals declared themselves appalled and asked that whatever was necessary be done. The final cost, established by the court-appointed expert, amounts to 1'311'848 fr. 64, from which the first-instance judges deducted the works ordered during construction (124'184 fr. 25), the additional works ordered directly by the principals (86'700 fr.) and the works ordered after the architect's departure (79'158 fr. 24). The overrun retained is 210'000 fr. compared with the estimate of 22 April 2008.

Procedure: The architect sued for payment of his fees (balance of 84'962 fr. 35). The principals filed a counterclaim for damages of 350'000 fr. The Civil Court awarded the architect a balance of 43'333 fr. 65, after reducing his fees by 30% (41'628 fr. 70) because of his fault, while denying any damage to the principals for lack of allegation and proof of different decisions. The Court of Appeal dismissed the appeal. Before the Federal Supreme Court, the principals seek set-off of the 210'000 fr. overrun against the fee balance, that is, payment of 166'666 fr. 35, and allege arbitrariness in the establishment of the facts (art. 97 para. 1 FSCA) as well as a violation of art. 398 CO. The respondent seeks dismissal of the appeal.

Main question: Have the principals established damage resulting from frustrated reliance, that is, would they have made different decisions and avoided certain costs had they received an accurate estimate?

Considerations

Admissibility and statement of facts: The appeal in civil matters is admissible (arts. 72, 74 para. 1 let. b, 75, 90 FSCA), the amount in dispute exceeding 30'000 fr. The statement of facts in the cantonal decision, taken over almost verbatim from the first-instance judgment, does not satisfy the requirements of art. 112 para. 1 let. a and b FSCA. The Federal Supreme Court rectifies it ex officio, exceptionally, in the interest of procedural economy (art. 105 para. 2 FSCA). Criticism of the statement of facts is subject to the strict principle of allegation (art. 106 para. 2 FSCA), and appellate-style criticisms are inadmissible.

Nature of the contract and distinction of liabilities: The global architect's contract is a mixed contract, subject to mandate rules for the services at issue. The architect's liability for a cost overrun (art. 398 paras. 1-2 CO) must be distinguished from his liability as site manager for additional costs resulting from defective performance. Liability for a cost overrun presupposes four cumulative conditions: breach of a duty of care, fault (presumed under art. 97 CO), damage and causation. The estimate is a forecast that the architect must prepare with diligence, informing the principal of its degree of accuracy and carrying out continuous cost control. A tolerance margin of 10% is accepted for new constructions under SIA Standard 102 (2003). Beyond that, the architect must compensate the frustrated-reliance damage.

Concept of frustrated-reliance damage: The damage does not lie in the difference between the anticipated cost and the final cost, because the value of the work corresponds to its cost. It consists in the fact that the principal would have made different decisions had he received an accurate estimate, for example by giving up certain works or opting for a less costly work. The subjective value of the work for the principal must be considered, that is, the difference between the objective value of the building and its subjective utility. There is no damage if the principal would have had the work carried out without change in any event. It is for the principal to prove, on the balance of probabilities, that he would have avoided certain costs.

Breach of the duty of care: The Federal Supreme Court notes that the breach of the architect's duty of care, in the estimation of costs and in…