Facts
The dispute concerns the area plan (PQ) "En Muraz" of the commune of Yens (VD), adopted by the Communal Council on 11 October 1993 and approved by the Cantonal Council of State on 31 August 1994. Its regulations (RPQ) provide, in particular, for implementation in stages (Arts. 1, 7, 17 and 19 RPQ), an internal connecting road linking the Chanta-Merloz (north) and Sus-Vellaz (south) paths (Art. 14 RPQ), and prohibit the issue of building permits before the road accesses and facilities are completed (Art. 31 RPQ). The PQ has not been implemented; it appears in the general zoning plan (PGA) of 2010 as special plan No. 3.
In 1998-2000, an initial project of 16 housing units had been annulled by the Vaud Administrative Court (judgment AC.1999.0080 of 28 June 2000), on the ground that the connecting road and the adaptation of the paths had to precede the permit. A request to abandon or revise the PQ, filed in 2014 by the Association of Residents of the East of the Village of Yens and others, was rejected; that decision was confirmed by the Federal Supreme Court (judgment 1C_387/2016 of 1 May 2017).
The developer [X. SA] prepared a project of 13 buildings totalling 42 housing units, with facilities, including a access road. An accessibility study (office [A.A.] , 19 May 2014) selected variant No. 5 "bidirectional South": vehicle access only from the south (Sus-Vellaz path, 4.5 to 5.5 m), northern access (Chanta-Merloz path, 3.5 m) reserved for emergency vehicles, cycles and pedestrians, with a swivel barrier. Two projects were put up for public inquiry from 13 May to 11 June 2015 (CAMAC 149507 for the housing units and the connecting road; CAMAC 152353 for the access road, the retention basin and the facilities). All special authorisations were granted. By decisions of 13 October 2015, the commune dismissed the objections and issued the building permits.
By judgment of 31 October 2017, the Court of Administrative and Public Law of the Vaud Cantonal Tribunal dismissed the appeals of the Association of Residents and others and of [A.] and [B.] (neighbouring owners). It admitted the simultaneous issue of permits for the housing units and the facilities, and held that the closure of the Chanta-Merloz path to individual traffic and the layout of the street-square as a cul-de-sac remained compatible with the PQ and Art. 63 RPGA.
The appellants [A.] and [B.] (case 1C_655/2017) and the Association of Residents and others (case 1C_661/2017) brought public law appeals before the Federal Supreme Court. The Association obtained suspensive effect by order of 10 January 2018. The Cantonal Tribunal and the municipality seek dismissal; the developer does likewise. The DGMR notes that no 30 km/h zone applies to the paths of the PQ.
Considerations
The two appeals are joined (Art. 24 FCPA and Art. 71 FSCA). Directed against a decision in public building law, they are admissible as public law appeals (Arts. 82 et seq. FSCA). The appellants [A.] and [B.] and [Z.] , owners of neighbouring plots, have a legitimate interest and standing (Art. 89 para. 1 FSCA); the standing of the Association and the other appellants may be left undecided.
The Federal Supreme Court reviews the application of cantonal and communal law only from the angle of arbitrariness (Art. 9 Cst.), with an enhanced duty of reasoning under the principle of allegation (Art. 106 para. 2 FSCA). A solution is arbitrary only if it is untenable, manifestly contrary to the actual situation, or adopted without objective grounds in violation of a clear right.
On implementation in stages (Arts. 1, 7, 17 and 19 RPQ), the complaint is rejected. These provisions contemplate the scenario of staggered execution (economic reasons, distinct owners) in order to avoid buildings lacking facilities. Nothing indicates that this objective would be compromised by carrying out, all at once and by a single owner, all the building possibilities.
On the simultaneous issue of the permit for the connecting road and the housing units (Arts. 14 and 31 RPQ), the complaint is likewise rejected. The Cantonal Tribunal validly abandoned the strict literal interpretation adopted in 2000, which obliged the builder to complete the facilities without any assurance of authorisation for the housing units. The solution adopted corresponds to the regime of Art. 104 para. 3 LATC and is compatible with Arts. 19 and 22 para. 2 let. b SPA, which require that the facilities be legally and technically secured at the latest before the end of the works. No indication suggests that these requirements will not be met.
By contrast, on the conformity of the access road with the plan (Arts. 2, 14 para. 1 RPQ, 63 RPGA), the complaint is upheld. The plan contains arrows indicating mandatory directions of traffic and two accesses, north and south; Art. 2 RPQ provides that vehicles access the area by a road linking the two paths. No provision of the regulations grants the municipality the freedom to suppress the northern access. The minor derogation (Art. 76 RPGA,…