Facts
The voters of the Municipality of Rothenburg (Canton of Lucerne) on 23 November 2015 adopted a new version of Art. 55 of the Building and Zoning Regulations (revBZR), which governs the erection of mobile telephone installations. Swisscom (Schweiz) AG, Sunrise Communications AG and Orange Communications AG (now Salt Mobile SA) lodged objections to this regulatory amendment, which were unsuccessful.
On 27 September 2016 the Cantonal Government of the Canton of Lucerne partially upheld the administrative appeal filed jointly and dismissed it for the remainder. The contested paragraphs 4-7 of Art. 55 revBZR provide for a cascade model: Priority 1 requires clarification of whether a site within the building zone is substantially more advantageous where a site outside the building zone is also possible; Priorities 2 and 3 contain a minimum distance of 100 m from residential uses as well as the exclusion of school facilities in Priority 3; paragraph 5 requires a functional connection in pure residential zones, in the core zone and in the work/residential zone; paragraph 6 prohibits visually perceptible antennas in the spot zone, the spot zone extension, the protection zones and on protected objects, as well as within a distance zone of 100 m from these; paragraph 7 contains requirements concerning aesthetic and architectural design.
By judgment of 28 June 2017 the Cantonal Court of Lucerne dismissed the administrative court appeal and held the cascade model to be compliant with federal law and not in breach of fundamental rights.
The appellants lodged an appeal in public law matters with the Federal Supreme Court and requested, among other things, the deletion of Priority 1, of the phrase 'ohne Schulanlagen und' (without school facilities and), of the minimum distance rule in Priorities 2 and 3, of the spot zone extension in paragraph 6, of the distance zone in paragraph 6, and of the aesthetics clause in paragraph 7, as well as the obtaining of an expert opinion on intangible immissions. The Municipality and the Cantonal Court requested dismissal. The President of the First Public Law Division rejected the application for suspensive effect on 12 December 2017.
Considerations
The Federal Supreme Court entertained, as an abstract review of norms, an appeal in public law matters against a final cantonal decision on a municipal building and zoning regulation (Art. 82 lit. b FSCA). The appellants, as mobile telephone operators, are virtually affected and have standing to appeal (Art. 89 para. 1 FSCA). In reviewing enactments, restraint applies: an enactment is annulled only if it cannot be interpreted in a manner consistent with the Constitution or federal law. The compatibility of municipal provisions with federal law is subject to the same assessment.
On the federal legal starting point, the court held: the assignment of zones is in principle a matter for cantonal and municipal law. A cascade model and a negative planning approach are permissible. However, mobile telephone installations outside the building zone require an exceptional permit under Art. 24 SPA, and the principle of separating building and non-building areas applies. Immission protection is comprehensively governed by federal law in the EPA and the NIRO. Intangible immissions may justify restricting mobile telephone installations in residential zones, but not far-reaching prohibitions of infrastructure installations serving the general interest.
On the complaints concerning the facts and the expert opinion: the assumption of intangible immissions caused by mobile telephone installations is a question of fact, reviewable only for arbitrariness. The appellants were unable to demonstrate that the Cantonal Court's assumption was obviously incorrect, so no expert opinion was necessary and the right to be heard was not infringed. The significance of intangible immissions in different zones is a question of law.
On Priority 1 (Request 2a): the provision reverses the precedence of the building zone as a site over the non-building area, since a site outside the building zone would only be considered where it is substantially more advantageous. This contradicts the federal requirements and does not permit a interpretation consistent with federal law. Priority 1 is to be annulled without replacement.
On the phrase 'ohne Schulanlagen und' in Priority 3 (Request 2b): intangible immissions are to be restricted to zones serving residential purposes. A need for protection of school users against intangible immissions is not apparent, and extension to work zones lacks sufficient public interests. The phrase is to be annulled without replacement.
On the minimum distance rule in Priorities 2 and 3 (Request 2c): the rule could exclude the use of a zone-conforming zone in substantial parts, which is problematic. However, since the distance is formulated only as a rule and allows exceptions, an application consistent with federal law is possible. The request is to be dismissed.
On the inclusion of the core zone and the work/residential zone in paragraph 5 (Request 2d): both zones permit predominantly residential use, so the protective interest against intangible immissions also prevails there. The functional connection is therefore consistent with federal law. The request is to be dismissed.
On the spot zone extension and the prohibition in paragraph 6 (Request 2e): the restriction rests on a sufficient public interest in protecting village centres and protected objects. Exceptions are permissible, and the insertion of 'in der Regel' (as a rule) is not required. The request, including the subsidiary request, is to be dismissed.
On the distance zone of 100 m in paragraph 6 (Request 2f): this rule significantly restricts the choice of site and permits no exceptions, since paragraph 6 contains no…