Facts

The dispute opposes [X. SA] , the building owner and counterclaim defendant (the appellant), to two individual architects and the company [M. Sàrl] , claimants (the respondents). The architects were engaged by the owner of a plot of land in Chêne-Bougeries, after the adoption of a local development plan on 10 March 2010, to implement a construction project for two residential and commercial buildings with an underground car park.

On 4 and 6 April 2011, the architects and the building owner signed a global architect's contract subject to SIA Regulation 102 (2003 edition). The theoretical maximum SIA fees amounted to CHF 2,164,403 excl. VAT; the parties contractually reduced them to CHF 1,320,286 excl. VAT (61%), based on a construction cost of CHF 13,545,788. The building owner was responsible for project ownership management, and the general contractor [N. SA] for coordination and management of the site.

The building permit application was filed on 8 December 2011 and the authorisation was issued on 17 February 2014. The building owner paid three advance payments totalling CHF 684,300. Tensions arose in spring 2013. The architects delivered the provisional execution plans on 28 August 2014, within the time limit set. On 10 September 2014, the building owner terminated the architects' mandate with immediate effect pursuant to art. 404 para. 1 CO.

The parties submitted the dispute to an arbitral tribunal sitting in Geneva, under an arbitration agreement of 29 April 2016. The architects claimed CHF 176,792.75 incl. VAT with interest at 5% from 10 September 2014, in particular for the provisional plans and compensation for termination at an untimely moment. The respondent filed a counterclaim for restitution of CHF 57,035.30 (from 31 January 2012) and CHF 17,196.60 (from 28 February 2014). By final award of 20 October 2017, the arbitral tribunal ordered the respondent to pay CHF 163,063.77 incl. VAT with interest at 5% from 10 September 2014 and dismissed the parties' remaining claims.

The respondent filed a civil law appeal with the Federal Supreme Court on 30 November 2017, seeking annulment of the award and remittal to the arbitral tribunal. The respondents seek dismissal of the appeal. The arbitral tribunal explained its fee calculation in its determination, referring to item 4.41 of Annex 2 and to the allocation key in Annex 7 of the contract.

Considerations

The civil law appeal is admissible against a domestic arbitral award under the conditions of arts. 389 to 395 CPC (art. 77 para. 1 let. b FSCA). Since the parties did not exclude arts. 353 to 395 CPC by opting out in favour of arts. 176 to 194 PILA, only the grounds exhaustively listed in art. 393 CPC are admissible; direct violation of federal law within the meaning of art. 95 let. a FSCA cannot be invoked. The appeal is purely cassatory (art. 77 para. 2 FSCA).

As regards the fees for the provisional execution plans, the appellant invokes arbitrariness within the meaning of art. 393 let. e CPC, arguing that these plans were unusable. The Federal Supreme Court recalls that arbitrariness in findings of fact presupposes a manifest contradiction with the case file, and not a disagreement with the assessment of evidence. The appellant challenges the arbitral tribunal's assessment of the plans and expert reports, which is inadmissible. The complaint of violation of the right to be heard (art. 393 let. d CPC in conjunction with art. 29 para. 2 Cst. and art. 190 para. 2 let. d PILA) also fails: the arbitral tribunal correctly held that the architects had calculated their fees on the basis of CHF 1,320,286 excl. VAT, and the offsetting between items, carried out within the limits of the claims, falls under the principle of party disposition (art. 58 para. 1 CPC) and does not violate the right to be heard.

Concerning compensation for termination at an untimely moment, the appellant invokes a manifest violation of law (art. 393 let. e CPC) of art. 1.12 para. 2 of SIA Regulation 102 and of art. 404 para. 2 CO. The Federal Supreme Court notes that this complaint, which concerns the interpretation of a clause according to the principle of good faith, may not satisfy the requirement of a manifest violation of substantive law; the question may nevertheless be left open. The clause is indeed interpreted in the architects' favour by part of the legal doctrine (PICHONNAZ; TERCIER/BIERI/CARRON), so that the application made by the arbitral tribunal is not arbitrary. The complaint is dismissed.

On the other hand, as regards the counterclaim for restitution of CHF 57,035.30 corresponding to 4% of the second advance payment for detailed studies, the appellant invokes a violation of the right to be heard and a finding…