Facts

The Bisse du Rô path connects Plan Mayen (above Crans-Montana) to the Ertentse valley, in the territory of the municipality of Icogne (VS). It is a hiking route forming part of the main cantonal network of leisure mobility routes within the meaning of the LIML (RS/VS 704.1). A preliminary study dated 30 January 2013 indicates that the bisse had been replaced in 1946 by a tunnel and that numerous measures to restore the water flow and improve the path were planned. The passage at the Dévaloir du Noir, crossing a high schist wall and exposed to falling rocks, was particularly dangerous; a footbridge was planned to avoid it.

On 7 November 2014, the Icogne Municipal Council put a building permit application out to public inquiry. The structure is 120 m long, overhangs the valley by a maximum of 70 m and is held by cables passing over support frames inclined at 6.5 m, anchored in the wall. The project gave rise to objections from the Swiss Foundation for the Protection and Development of the Landscape and from Mountain Wilderness Switzerland (the objectors).

On 13 January 2016, the Council of State of the canton of Valais approved the amendment of the route plan and the construction plan for the footbridge, subject to various conditions, and dismissed the objections. The footbridge, justified on safety grounds, was preferred to tunnel and gallery variants, which were more costly and uncertain. The impact in the cantonal landscape protection zone could be mitigated by measures imposed by the cantonal Forest and Landscape Service.

By judgment of 13 January 2017, the Public Law Division of the Cantonal Court of the canton of Valais dismissed the objectors' appeal. It held that the footbridge could be examined independently of the other facilities, in the absence of interaction, and that an overall assessment within the meaning of Art. 8 EPA, as well as coordination or planning of the route, was not necessary. Reports from two specialists indicated that the passage was threatened by schist slabs resting on a rock mass located some twenty metres above the path, and that remediation works were too dangerous. The alternative route below (Chemin de la Montagne) had been built without authorisation. The area lay within the landscape protection zone under Art. 15 of the amendment to the RIC, but the structure could be treated as the transformation of an existing installation; according to the impact notice of 22 October 2014, it would remain invisible from most viewpoints. Safety reasons could therefore outweigh the interest in protecting nature and the landscape.

The two associations have lodged a public law appeal with the Federal Supreme Court, seeking annulment of the cantonal judgment; suspensive effect was granted on 10 March 2017. The municipality of Icogne seeks dismissal of the appeal. The Federal Office for the Environment (FOEN) considers that there is no breach of Art. 8 EPA, but that a less landscape-intrusive solution (a lighter structure) should be examined. The cantonal authorities waived the right to submit observations.

Considerations

On admissibility, the appeal is directed against a final decision of the last cantonal instance and concerns the approval of a route plan and a structure; it is admissible as a public law appeal (Art. 82 et seq. FSCA). The associations are not listed in Art. 14 para. 1 FHTA, but that provision does not exclude organisations recognised under other provisions of federal law, in particular Art. 12 NCHA. Having standing to act in the field of nature and landscape protection (Art. 12 NCHA, Art. 1 DORAO), they may appeal provided the complaint concerns a federal task, which is the case here since the installation would be subject to Art. 24 et seq. SPA.

On the complaint of breach of Art. 8 EPA (overall assessment), the Federal Supreme Court recalls that impacts must be assessed individually, collectively and in their combined effect, without spatial, temporal or material limits, and that a project may be carried out in stages provided that an overall assessment is possible. In this case, the facilities are distributed linearly over about six kilometres, the footbridge can be built independently of the other facilities, the impacts do not significantly add up and the impact of the other facilities appears secondary. The project may further be subject to an overall assessment in the balancing of interests. The complaint is dismissed.

On arbitrariness in the application of Art. 8 para. 3 LIML and breach of coordination (Art. 25a SPA), the cantonal court could hold without arbitrariness that the single overall decision concerns the plan for the section and the related structures, and not all the structures along the route; this interpretation is confirmed by Art. 5 and 9 LIML and does not preclude implementation in stages. As for Art. 25a SPA, the coordination requirement is respected since the decision was made by the sole competent authority, the Council of State, which is also competent for the other elements.

On the justification of the project, planning authorities have discretion but must weigh the interests (Art. 2 para. 3 SPA, art. 3 NCHA). The geological expert reports, consistent with one another and confirmed by the 2016 opinion of the Cantonal Geologist, establish a real and lasting danger of falling rocks on the passage. The path, a mountain path, is accessible to a very diverse public from a tourist resort, which justifies a higher level of safety. The complaint is dismissed. Regarding the variants (art. 3 NCHA, Art. 18 para. 1ter NCHA), federal law does not require a detailed analysis of all alternatives, but the examination must be more thorough when art. 3 NCHA is at issue. The comparison addressed cost,…