Facts

AlpTransit Gotthard AG (ATG), a subsidiary of the SBB, is building the Ceneri Base Tunnel. The awards are subject to the PPA. As early as 1997, the SBB concluded with the Azienda Elettrica Ticinese (AET) an energy supply contract for construction power in Ticino, which after the entry into force of the ESA (2008) was amended by four addenda.

In 2007 the ATG awarded lot 813 (materials management) and in 2008 lot 814 (Sigirino landfill) to two consortia, consisting of Agir AG, Agir Aggregat AG and Ennio Ferrari SA. According to the contract for work and the tender documentation, the ATG procures the electricity; the AET supplies it, and the contractors must pay for the electricity, whereby the AET invoices the companies directly.

In 2013 the consortia concluded with the Elektrizitätswerke des Kantons Zürich (EKZ) an electricity supply contract for 2014 to 2016. The AET refused network access, as the ATG was the holder of the connection points and the consortia were not final consumers entitled to free network access.

At the request of the EKZ and the consortia, the Federal Electricity Commission (ElCom) ruled on 13 November 2014 that the AET must grant network access and provide the metering data; it was also established that network access had been wrongly refused. It declined to entertain the claim for damages. The Federal Administrative Court, by judgments of 13 November 2015 (A-213/2015 and A-257/2015), set aside the decisions because the ATG and not the consortia was the final consumer, and dismissed the requests for network access.

The EKZ and the consortia lodged appeals in public law matters with the Federal Supreme Court (2C_12/2016 and 2C_13/2016). The Federal Supreme Court joined the proceedings. The respondents (ATG and AET) requested dismissal.

Considerations

The appeals are admissible (Art. 82 lit. a, Art. 86 para. 1 lit. a, Art. 90 FSCA). The subject matter of the dispute is not a procurement relationship (Art. 83 lit. f FSCA). The appellants are formally aggrieved and particularly affected (Art. 89 para. 1 lit. a and b FSCA). A possible loss of current interest regarding lot 813 does not matter, as there is a sufficient interest in clarifying the legal question (Art. 89 para. 1 lit. c FSCA; BGE 139 I 206).

Under Art. 13 para. 1 ESA, there is a right to non-discriminatory network access for 'third parties', which is not limited to final consumers and does not presuppose a consumption site. Fixed final consumers with an annual consumption of less than 100 MWh per consumption site are excluded from network access (Art. 6 paras. 2 and 6 ESA; Art. 11 ESO). The qualification as a final consumer and consumption site is therefore only a negative, not a positive, prerequisite for the claim (BGE 141 II 141 E. 5.3).

The legislative history and systematic structure of the ESA confirm that network operation and electricity supply are unbundled. Outside the basic supply, electricity supply contracts are governed by private law and economic freedom. Since everyone may conclude electricity supply contracts, network access in principle belongs not only to final consumers but to all market participants. A network access claim is therefore not necessarily limited to final consumers within the meaning of Art. 4 para. 1 lit. b ESA.

The consortia are neither fixed final consumers nor do they fulfil a statutory exception from network access. They draw more than 100 MWh per year, no grounds for refusal under Art. 13 para. 2 ESA were asserted, and the absence of an individually negotiated supply contract under Art. 11 para. 2 ESO is not a positive prerequisite for the claim, but only concerns the basic supply. The EKZ concluded an electricity supply contract with the consortia, so there is no impediment.

Whether the consortia or the ATG are final consumers within the meaning of the law, and whether the contract…