Facts
The Verein C. (client, defendant, respondent) and the then [B. AG], now A. AG (contractor, plaintiff, appellant), concluded on 17 July 2006 a contract for architectural services for the extension or partial superstructure of the 'C.'. Clause 2.2 agreed a 'lump sum according to cost estimate' with reference to a fee based on construction costs according to Annex 6 and estimated construction costs of approx. CHF 10'500'000.--. Clause 2.3 provided for a basic fee of 'lump sum CHF 380'000.00' plus 7.6% VAT, derived from partial services of CHF 692'875.-- (6'025 hours) less a reduction of around 45%.
According to the cost estimate of 22 August 2006, the project costs were to amount to CHF 16'261'050.--. In addition, the parties agreed a fee up to and including the building permit of CHF 148'488.-- (paid) and a fee for the realisation from the tender onwards of CHF 457'300.--. On 13 July 2007 they concluded a supplementary agreement: an additional fee for extra effort due to the public tender of CHF 26'900.-- and an additional fee of CHF 150'000.-- in total for 'additional costs of any kind'.
From 2008 onwards the client objected to information, planning, construction supervision, deadlines and additional costs. By letter of 29 January 2009 the contractor demanded a residual claim of CHF 209'180.--, which the client described on 6 February 2009 as contrary to the contract. In addition, there was an invoice of 15 April 2009 for CHF 24'479.-- (revision plans and bicycle shelter). The contractor brought debt enforcement proceedings against the client; the client raised objection (Rechtsvorschlag) in both proceedings.
The District Court of Arbon dismissed the contractor's action on 20 November/14 December 2015. The Thurgau Cantonal Court dismissed the appeal by decision of 28 June 2016: the contractor had not made substantiated statements regarding additional services arising from direct contracts between the client and third parties, and the application of SIA Standard 102 to the fee-relevant construction costs was rejected.
By civil law appeal of 9 September 2016, the contractor requested the annulment of the cantonal court's decision, alternatively its remittal. The respondent requested dismissal. The lower court waived a response.
Points in dispute:
- Interpretation of the contract: lump-sum fee or fee based on fee-relevant construction costs (Art. 18 CO, principle of reliance, in dubio contra stipulatorem)
- Entitlement to additional remuneration for additional services arising from direct contracts concluded by the client with third parties (Art. 394 CO, substantiation)
- Right to be heard and production of documents (folder plaintiff's exhibit 354, defendant's exhibits 33 and 34)
Considerations
The Federal Supreme Court reviews the facts only for obvious inaccuracy (arbitrariness) under Art. 105 para. 2 FSCA and applies the strict principle of complaint (Rügeprinzip) under Art. 106 para. 2 FSCA. New facts and evidence are admissible under Art. 99 para. 1 FSCA only insofar as the decision of the lower court gives cause for them. The request for further production of documents was not admitted, because the appellant did not show that only the Cantonal Court gave cause for it.
On the interpretation of the contract, the Federal Supreme Court holds that the actual, mutually shared intention of the parties applies first (Art. 18 para. 1 CO). If this cannot be proven, the presumed intention must be determined according to the principle of reliance from the wording, context and circumstances at the time the contract was concluded; the interpretation is a question of law. The appellant supplemented the facts in free discussion without demonstrating arbitrariness, which is why it was largely not entered into.
The Federal Supreme Court confirms the interpretation of the lower court, according to which a lump-sum fee was agreed. The lump sum according to the cost estimate (clause 2.2), the lump-sum fee of CHF 380'000.-- (clause 2.3) and the additional lump-sum amounts for additional costs (supplementary agreement, clause 7) point to a fixed remuneration that does not depend on…