The client (appellant, plaintiff), based in [U.] , provides services in the field of civil and military aviation. The contractor (respondent, defendant), [B. AG] , based in [V.] , operates in real estate and construction, in particular as total or general contractor.
By a general contractor work contract dated 3/7 July 2003, the client commissioned the contractor to build the new air traffic control centre [W.] . For the sanitary installations, the contractor submitted a 'Produkteliste Sanitär' (sanitary product list) on 23 March 2004, in which [C. AG] offered, as a contractor variant, products of the '[F.] ' system of [G. AG] instead of the products of the manufacturer '[E.] ' provided for in the bill of quantities. The award to [C. AG] was signed in April and May 2004 by both parties as well as by the planner [H. AG] and its subcontractor [I. AG] .
The acceptance of the entire building took place on 30 June 2005. At the end of 2009, the client had all red brass fittings of the reverse osmosis water system in buildings A to E replaced with chrome steel fittings. It regards the installation of red brass fittings instead of chrome steel fittings as a defect. The contractor counters that the parties had agreed on a contractor variant with red brass deviating from the bill of quantities, that the client had known of the use of this material, and that it had approved the installation.
On 29 June 2013, the client filed an action with the Commercial Court of the Canton of Zurich, seeking replacement of the red brass fittings with chrome steel fittings (principal claim) or with equivalent fittings (alternative claim), as well as payment of CHF 67'380.65 and CHF 83'834.50 plus default interest. It gave notice of the dispute to [H. AG] , which did not declare itself; the proceedings continued without it.
By judgment of 26 September 2016, the Commercial Court dismissed the action. It left open whether the alleged change of order had validly come about, and held that the deviation in the choice of material should have been obviously recognisable at acceptance to the client, which was professionally advised; any defect was therefore approved under Art. 163 SIA Standard 118.
By civil law appeal dated 11 November 2016, the client requests that the judgment be set aside and the action upheld, or alternatively that the matter be remitted for the conduct of taking of evidence. The contractor requests dismissal. The lower court waived a response.
Considerations
The appeal concerns a civil matter (Art. 72 FSCA) against a final decision (Art. 90 FSCA) of a higher cantonal specialist court for commercial disputes (Art. 75 para. 2 lit. b FSCA). The appellant is the losing party and the time limit (Art. 100 para. 1 FSCA) has been observed; the appeal is admissible, subject to sufficient reasoning (Art. 42 para. 2, Art. 106 para. 2 FSCA).
Under Art. 163 SIA Standard 118, which the parties undisputedly declared to be part of the contract, a recognised defect is deemed approved if the site management, during the joint inspection, expressly or tacitly waived its assertion. For obvious but unchallenged defects, the tacit waiver is irrebuttably presumed (Art. 163 para. 2 SIA Standard 118). A defect is obvious if it is immediately apparent upon mere inspection; the decisive factor is the expertise expected of the client or inspector. The lower court found that the copper- or bronze-coloured red brass fittings differ clearly from the silver-coloured chrome steel fittings; the client was professionally advised by its planner and that planner's subcontractor, and the sanitary installations were inspected in all five buildings, including the material of the cold and hot water pipes. Red brass fittings were, moreover, widely used at the time of acceptance.
The appellant complains that the lower court misunderstood obviousness, since the non-conformity with the contract must also be obvious, and that with a bill of quantities of around 380 pages it could not be required to recognise every deviation. The Federal Supreme Court holds that obviousness covers both the actual condition and its non-conformity with the contract. The client need not know the contract by heart; what matters is that the deviation from the contract, which is naturally known, is obvious. This is the case with a contractually prescribed choice of material that is clearly distinguishable by colour, which the appellant does not dispute. The lower court therefore correctly interpreted Art. 163 para. 2 SIA Standard 118.
The complaint of a violation of the right to be heard due to the failure to conduct an inspection in situ also fails. The fittings, which are clearly described as 90-degree elbow pieces with a diameter of 22 mm, cannot be confused with fixtures; it has not been shown how an inspection in situ could have yielded a different result. Nor is the argument convincing that the approximately twelve visible fittings are not representative: the choice of material was prescribed uniformly for all fittings, so it is not comprehensible why the deviation should be obvious only for the visible pieces. The lower court affirmed an obvious defect without violating federal law.
On fraudulent concealment, the Federal Supreme Court holds: under Art. 370 para. 1 CO, the contractor remains liable despite approval for defects intentionally concealed. Fraudulent concealment requires that the defect be unknown to the client and known to the contractor, that the contractor knows or must know of the…