Facts

The complainant [A.] is a neighbour of a property in Rickenbach (Municipality of Schwyz), which lies in zone W2D (two-storey dense residential zone). The respondents (developers) intended to build a single-family house with an annexed flat on the south-western part of their plot.

On 28 May 2014 the Municipal Council of Schwyz granted the building permit and dismissed the neighbour's objection. On 3 March 2015 the Cantonal Government of the Canton of Schwyz upheld the neighbour's appeal and quashed the permit, because the permissible floor area ratio had been exceeded.

The developers amended the project. On 29 May 2015 the Municipal Council approved the amended project subject to conditions; a renewed objection by the neighbour was dismissed. On 6 July 2015 the Cantonal Government referred the appeal to the Administrative Court of the Canton of Schwyz, Chamber III, which dismissed the appeal on 18 February 2016.

The neighbour lodges an appeal in public law matters with the Federal Supreme Court and requests that the decision be set aside and the building permit refused, or alternatively that the matter be remitted. He complains of a violation of the right to be heard (failure to conduct an inspection on site) and of arbitrariness in the establishment of the facts and in the application of the law. The request for suspensive effect was dismissed by order of 24 May 2016.

The dispute concerns in particular how the concept of natural terrain (§ 60 PTA SZ, Art. 22 para. 2 BR Schwyz) is to be interpreted where the plot was filled more than 30 years ago, and whether the excess heights of 1.60 m on the south façade and 0.70 m on the east façade are permissible.

Considerations

The Federal Supreme Court has jurisdiction (Art. 82 let. a, Art. 86 para. 1 let. d, Art. 90 FSCA) and the neighbour has standing as a directly affected party (Art. 89 para. 1 FSCA). The complaint of insufficient reasoning was not raised as an independent complaint and therefore need not be examined. Findings of fact may only be challenged on the ground of manifest error (arbitrariness) (Art. 105 paras. 1 and 2 FSCA); federal law is examined freely, while other cantonal law is examined only for arbitrariness (Art. 95 FSCA).

The right to be heard (Art. 29 para. 2 Cst.) has not been violated. Ordering an inspection on site lies within the discretion of the authority and is only required where the facts cannot be established in another way. Relying on photographs, plans with contour lines and publicly accessible internet data, and on the undisputed facts (fill placed more than 30 years ago, gradation of the terrain on the south façade), the Administrative Court could form its conviction without arbitrariness; an inspection would not have yielded any material new findings.

As regards the interpretation of natural terrain, the Federal Supreme Court notes that the terms in § 60 PTA and Art. 22 para. 2 BR are indeterminate legal concepts. The Administrative Court has developed its practice from a static to a dynamic understanding: the criterion of non-ascertainability loses importance, and a deviation from the currently shaped terrain is only required where it is manifest and leads to results that are untenable under building police law. This interpretation is defensible and not arbitrary.

The Intercantonal Agreement on the Harmonisation of Building Terminology (IVHB) has no positive pre-effect. For the Canton of Schwyz it had not yet had to be implemented at the time of the building permit (implementation period of three years after accession, effective 1 January 2013), and at most it serves as an aid to interpretation. The practice of the Administrative Court is comprehensible and therefore not open to objection; the cantonal authorities are not obliged to interpret the provisions in conformity with the IVHB. Judgment 1C_531/2012 is distinguishable, since there the interpretation clearly contradicted the wording.

The fills took place more than 30 years ago, long before the…