Facts
Parties and proceedings: The appellants (owners of the servient plot No. xxx) and the respondent (owner of the dominant plot No. www) dispute the content and scope of a footpath and vehicular right of way entered in the land register of the municipality of U. The District Court of March partially upheld the action after an inspection on site. The Cantonal Court of Schwyz, 1st Civil Chamber, partially amended the judgment on 19 May 2016 on appeal by the defendants. The appellants lodged a subsidiary constitutional complaint with the Federal Supreme Court (judgment of 15 March 2017, 5D_103/2016).
Easement agreement (1965): As a connection between [D.] strasse and the purchased parcel No. www, an unrestricted footpath and vehicular right of way was granted over the already prepared path on plot No. xxx, in exchange for assuming joint maintenance liability for the access road. The joint maintenance obligation was abolished in 1971; since then the owner of the servient plot has borne the maintenance alone. Both plots are built over with residential houses.
Local conditions: The two-metre-wide access road leads from [D.] strasse uphill in a curve behind the residential houses to a farmstead. The dominant plot does not adjoin the access road; between the edge of the road and the plot boundary lies a narrow strip of land belonging to the servient plot, which has been planted since 1999 with a green hedge (with wooden posts and steel posts). The entrance today measures four metres, bordered on the left by a wood and natural hedge of thuja trees and on the right by the green hedge. Three boulders lie in the curve of the access road.
Subject matter of the dispute and requests: On 27 November 2014 the plaintiff requested the removal of the boulders and the green hedge, so that the entrance would be nine metres wide. The District Court ordered the defendants to remove the green hedge up to 9 m from the westernmost boundary point, struck the request concerning the three boulders from the record due to acknowledgement of the claim, and dismissed the action for the remainder. The Cantonal Court set aside the striking from the record and additionally ordered the defendants to remove the three boulders in the left-hand bend.
Requests before the Federal Supreme Court: The appellants requested the complete annulment of the cantonal judgment, alternatively remittal. Suspensive effect was granted with regard to the green hedge. The Federal Supreme Court dismissed the appeal insofar as it was admissible; court costs of CHF 3,000.-- were imposed jointly and severally on the appellants, and no costs of the parties were awarded.
Considerations
Admissibility: The amount in dispute of CHF 30,000.-- does not reach the minimum threshold for an appeal in civil matters (Art. 74 para. 1 lit. b FSCA), and no question of fundamental importance is raised. The subsidiary constitutional complaint is therefore admissible (Art. 113 FSCA). Only the violation of constitutional rights may be complained of, and clearly and precisely substantiated complaints are required (Art. 106 para. 2 FSCA). The mere request for annulment is exceptionally sufficient because a violation of the right to be heard is alleged and the Federal Supreme Court could not itself decide the matter on the merits if the complaint were well founded.
Unlimited right of way: An unlimited right of way is neither spatially nor functionally restricted and guarantees direct access to the dominant plot. The needs of the dominant plot are decisive (BGE 117 II 536; BGE 139 III 404). The term 'prepared path' means an artificially constructed path or a path that permanently appears topographically. The cantonal court made no findings on the prepared path because the parties had not attached any independent meaning to this expression. Appellate proceedings do not serve to supplement the proceedings at first instance (BGE 142 III 413). In the disputed area between the road verge and the plot boundary, the cantonal court could arbitrarily-free assume an unlimited, unprepared right of way. In the area of the access road, however, the right of way is prepared and spatially defined.
Interpretation under Art. 738 CC: The starting point is the land register entry. If this is unclear, reference must be made to the title of acquisition, and only if this too is inconclusive may the manner of use exercised for a long period without challenge and in good faith be considered (Art. 738 paras. 1 and 2 CC; BGE 137 III 145). Since the title of acquisition yielded clear results, the long-standing exercise was legally irrelevant. The complaint of violation of the right to be heard for failure to consider the exercise is not upheld, since the cantonal court had addressed it. The complaint against the district court is inadmissible (Art. 114 in conjunction with Art. 75 para. 1 FSCA). The manner of exercise only shows that the easement is not narrower, but it does not exclude a wider scope (judgment 5C.199/2002).
Purpose and construction plan: The easement agreement aims at providing access to the dominant plot on foot and by vehicles for residential purposes. Against owners who did not participate in its establishment and who acquired in reliance on the land register, the purpose arising from the agreement or objectively recognisable purpose is decisive. Individual motives of the original parties remain disregarded (BGE 130 III 554; BGE 138 III 650). The construction plan of 1965 is not a land register document and was not known to the respondent, so it does not justify any restriction of the right of way. The assessment by the cantonal court is free of arbitrariness.
Circle of users: An unlimited right of way for residential purposes permits use by residents, their relatives and visitors, as well as by service providers necessary for residential use (tradespeople, taxis, furniture removals, heating oil deliveries). The supply of heating oil belongs to ordinary maintenance, so larger lorries may also be admitted (BGE 131 III…