Facts

The dispute concerns the approval by the Federal Office of Transport (OFT) of the plans for the railway project "Léman 2030 - Gare de Renens, enclenchements, 4ème voie Lausanne-Renens", which entails the expropriation of a separate and permanent right of superficies (DDP) held by the appellant [A.] on plot 433 of the Municipality of Renens, owned by the CFF.

On 25 April 2013, the CFF, the Transports Publics de la Région Lausannoise SA (tl) and the municipalities of Chavannes-près-Renens, Crissier, Ecublens and Renens (the project owners) signed an agreement on the management of the plan approval procedure. The CFF lead the community of applicants and represent it before the OFT, without however being designated as expropriating party. On 23 May 2013, the plans were submitted to the OFT in five sub-files, including sub-file 5 (extension of the m1 metro platform at Renens station and relocation of track 62 to the south), a tl project.

Following a public inquiry and the appellant's objection, the OFT partially approved sub-file 1 on 21 May 2014, a decision which became final. During the conciliation hearing of 9 July 2014, two variants avoiding encroachment on the DDP were examined; one was excluded by mutual agreement, the other (platform shortened to 65 m) was deemed problematic by the project owners. By decision of 16 January 2015, the OFT approved sub-files 2 to 5 with reservations and conditions and dismissed the objection.

The appellant appealed to the Federal Administrative Court (TAF), which partially granted the withdrawal of suspensive effect (file 3 in May 2015, then certain works of sub-files 2 and 4 on 20 January 2016). Finding a partial breach of the right to be heard, the TAF invited the OFT to supplement its reasoning, which it did on 15 March 2016. By judgment of 22 June 2016, the TAF dismissed the appeal, confirmed the approval of the plans, and remitted the file to the Federal Commission for Valuation for the fixing of the expropriation compensation, holding that the public interest in immediate and coordinated implementation outweighed the appellant's private interest in enjoying the DDP until 2020.

Before the Federal Supreme Court, the appellant seeks the annulment of the approval decision and obtained suspensive effect by presidential order of 15 September 2016. He invokes the lack of standing of the CFF to expropriate, for want of a valid delegation under art. 3 ComPurA, as well as the absence of sufficient public interest and the breach of proportionality. An urgent request for provisional measures, aimed at halting the construction site, was dismissed on 18 October 2016. The OFT maintains its decision, the TAF declines to take a position, and the CFF conclude that the appeal is inadmissible, or alternatively that it be dismissed.

Considerations

As to admissibility, the Federal Supreme Court notes that the request for annulment of the OFT's decision is inadmissible because of the devolutive effect of the appeal before the TAF (Art. 54 APA). However, read in light of the reasoning, the requests target the TAF's judgment, so that the appeal is in principle admissible. The appellant, who is particularly affected by the expropriation of his DDP, has standing to appeal (Art. 89 para. 1 FSCA). A press document produced by the CFF after the contested judgment is inadmissible (Art. 99 para. 1 FSCA), and new facts alleged by the parties, without any demonstration of arbitrariness, are not taken into consideration (Art. 105 para. 1 FSCA).

As to the first ground concerning the CFF's standing, the Federal Supreme Court leaves open the question of the admissibility of a new complaint, the latter being in any event unfounded. Under art. 3 ComPurA, the right of expropriation may be conferred on third parties. Art. 8 of the agreement of 25 April 2013, which refers to a "joint expropriation", is considered poorly drafted; the scheme of the agreement confers on the CFF only a steering and representative role, the documents of sub-file 5 having been prepared and signed by the tl, which are at the origin of the project and request the procedure with expropriation. The tl, holders of a fifty-year concession granted by federal decree of 18 December 1986 under Art. 5 RailA, enjoy the right to expropriate (Art. 3 para. 1 RailA and Art. 3 para. 2 let. b ComPurA). The fact that the expropriation ultimately benefits the CFF has no bearing on the identity of the expropriating party and will be examined in the weighing of interests.

As to public interest and proportionality, the Federal Supreme Court recalls that formal expropriation may only be exercised to the extent necessary for the purpose pursued (Art. 1 paras. 1 and 2 ComPurA), that the principle of proportionality in the narrow sense requires a weighing of interests, and that it examines these questions freely while showing restraint in the face of local circumstances and assessments (Art. 18 para. 1 RailA). The appeal, which is essentially based on the CFF's patrimonial interest (Romandy seat, hotel, shops), is appellate in nature and borders on admissibility (Art. 42 para. 2 and Art. 106 para. 2 FSCA), and does not criticise the meticulous weighing carried out by the TAF.

On the basis of a technical analysis compliant with the IP-RailO (DE 34.4), the TAF established that Renens…