Facts

The building client (two private individuals, respondents 1 and 2) entered into a general contractor work contract on 2 May 2011 with [A. GmbH] (contractor, plaintiff, appellant) for the new construction of a single-family prefabricated house. SIA Standard 118 (1977/1991) was agreed as a supplementary part of the contract.

The contract provided for submission of the building application by 16 May 2011, erection of the house in calendar week 35/2011 (29 August to 2 September 2011), and a fixed date for readiness for occupancy on 16 December 2011, provided that the building permit was available by 30 June 2011; otherwise the fixed date would be postponed by the duration of the later building release. The dates were subject to release by the building authority and to influences not attributable to the contractor.

By letter of 28 August 2011, the building clients invoked the non-binding nature of the work contract and, as a precaution, withdrew from the contract. On 18 May 2012 the contractor brought an action before the District Court of March for payment of CHF 77'811.45 and EUR 21'683.75 plus interest, with joint and several liability of the defendants. The District Court dismissed the action by judgment of 2 June 2014. The Cantonal Court of Schwyz, 1st Civil Chamber, dismissed the appeal by judgment of 9 June 2015.

By way of civil law appeal, the contractor essentially requested that the first-instance claims be upheld. The Federal Supreme Court rejected the application for suspensive effect by presidential order of 2 October 2015. The respondents requested dismissal with costs; the lower court waived a response.

The subject matter of the dispute concerned in particular the client's right of withdrawal under Art. 366 para. 1 CO (delay in completion), the necessity of setting a grace period, the consideration of time credits, the proportionality of withdrawal ex tunc, and the acceptance of an expert opinion or the disclosure of specialist knowledge of the judges under Art. 183 para. 3 CPC.

Considerations

The Federal Supreme Court examined the complaints regarding the facts under Art. 97 and 105 FSCA. It held that only manifestly incorrect (arbitrary) findings of fact may be challenged and that appellatory criticism of the assessment of evidence is inadmissible. Arbitrariness exists where the court has manifestly misjudged the meaning and scope of a piece of evidence, disregarded an important piece of evidence without objective grounds, or drawn untenable conclusions.

Regarding withdrawal under Art. 366 para. 1 CO, the Federal Supreme Court confirmed the view of the lower court that timely completion of the work could no longer be expected. Failure to meet a non-binding interim date does not in itself constitute delay, but the extent of the delay may allow conclusions about the probability of timely completion. For this assumption, the objective conviction of the court is sufficient; absolute certainty is not required. According to legal scholarship (Zindel/Pulver/Schott, Bühler, Koller), it is sufficient that the contractor will not be able to meet the date at an average work pace.

The appellant would therefore have had to show that the delay was so slight that no conclusion could be drawn that the final date would not be met, or to demonstrate within the framework of counter-evidence that the work could have been completed on time despite the backlog. The counter-evidence did not succeed: the assertions concerning comparable construction schedules (11 or 12 weeks) were not sufficiently substantiated, because the specific construction dates and the comparability of the projects were lacking. The burden-of-proof rule was immaterial, since the lower court did not assume a non-proof situation. The setting of a grace period was considered futile, as it does not alter time that has already elapsed, and the appellant provided no sufficiently substantiated information on the necessary construction time.

The time credits (delayed building permit by the ARE, changes to orders concerning the foundation) were rejected: the Federal Supreme Court left open whether the reaction of the ARE was relevant, since a shift of two weeks did not change the result. The…