Facts
The heirs of F. G.-H. are the owners of parcel No. 287 in Hergiswil (NW), located in the two-storey residential zone (Zone W2D). They intend to build a development of eight single-family houses on it. To this end, the heirs submitted the Sonnenberg development plan to the Hergiswil Municipal Council. During the public inspection period, four neighbours (the appellants, owners of directly adjoining parcels) filed objections.
By decision of 18 September 2012, the Municipal Council approved the development plan subject to conditions and requirements and subject to approval by the Building Directorate of the Canton of Nidwalden, and dismissed the objections. The Building Directorate dismissed the objectors' appeal on 26 November 2013 and approved the development plan on the same day. The Administrative Court of the Canton of Nidwalden dismissed the appeal lodged against this by judgment of 22 September 2014, insofar as it was admissible.
The appellants lodged a public law appeal with the Federal Supreme Court on 2 February 2015, requesting that the lower court's judgment be set aside and the matter be remitted to the Municipal Council. The Municipal Council, the State Chancellery and the respondent requested dismissal. The Administrative Court waived its right to comment. A request for suspensive effect was dismissed by presidential order of 3 March 2015.
The subject matter of the dispute was in particular: (1) the alleged nullity due to the lack of public inspection of the access plan and of buildings lying outside the perimeter; (2) the refusal to obtain a neutral expert opinion on the flood hazard; (3) compatibility with the coordination principle and the existing Untere Rüti development plan, since access is provided via parcel No. 1284, which lies outside the perimeter and on which a bicycle and waste container room is also planned.
Considerations
The public law appeal against the final cantonal decision on a development plan is admissible under Art. 82 lit. a and Art. 86 para. 1 lit. d FSCA; the appellants, as direct neighbours, have standing to appeal under Art. 89 para. 1 FSCA. The Federal Supreme Court applies the law ex officio (Art. 106 para. 1 FSCA), but in principle examines only the complaints raised under Art. 42 para. 2 FSCA. For complaints of violation of fundamental rights, including arbitrariness, a qualified duty to state complaints applies (Art. 106 para. 2 FSCA).
Regarding the alleged nullity due to defective public inspection: under Art. 33 para. 1 SPA, use plans must be made available for public inspection. The special building regulations (Art. 19 concerning parcel No. 1284) and the access plan were made available for public inspection, and the landowners and neighbours were notified in writing. No violation of federal law is apparent. Moreover, according to settled case law (BGE 138 II 501; 137 I 273), procedural defects only exceptionally lead to nullity and generally merely to voidability (BGE 129 I 361; 116 Ia 215).
Regarding the expert opinion question (right to be heard under Art. 29 para. 2 Cst.): anticipatory assessment of evidence is permissible if the authority is convinced and may, without arbitrariness, assume that further evidence would not change this conviction (BGE 136 I 229; 134 I 140). The natural hazards report by Schubiger AG, which the Municipal Council declared binding, shows a low hazard level in the torrent area of the Stampfbach. The object protection measures under Art. 32 BZR serve to protect the development itself, not neighbouring parcels. The Federal Supreme Court notes that the report convincingly and plausibly demonstrates that the hazard to neighbouring parcels already exists and is not increased by the project (Art. 28 BZR). The party expert opinion merely establishes that a localised increase cannot be entirely ruled out, but not a substantial additional hazard. Furthermore, the appellants did not substantiate any errors in the report. The Administrative Court was therefore entitled, without arbitrariness, to dispense with a further expert opinion.
Regarding coordination with the Untere Rüti development plan (Art. 25a para. 4 SPA): arbitrariness in the application of law exists only where the decision is…