Facts

The [C.] Generalunternehmung AG concluded a contract for works with [A. AG] (appellant) for interior metal doors for a new building of [B. AG] (respondent) in [U.] . Installation was carried out until 1 September 2014. Acceptance took place on 2 September 2014, and it was recorded as an 'insignificant defect' that the labyrinth rail would be installed on 5 September 2014. This installation took place on 5 September 2014.

By application dated 5 January 2015, the appellant requested the ex parte provisional registration of a builder's lien in the amount of Fr. 38'031.50 on the respondent's property. The Civil District Court of Basel-Landschaft East ordered the registration the same day. The appellant did not appear at the hearing on 29 January 2015. The respondent argued that the works had been completed on 1 September 2014 and that a minor defect (a loose rail) had been remedied on 5 September 2014. The Civil District Court ordered the deletion, because the four-month time limit under Art. 839 para. 2 CC had already begun to run before 5 September 2014. The Land Register Office carried out the deletion on 30 or 31 January 2015.

The Cantonal Court of Basel-Landschaft, Civil Law Division, dismissed the appellant's appeal by decision of 7 July 2015. The appellant lodged a complaint with the Federal Supreme Court on 12 August 2015, requesting that the decision be set aside and the lien registered, or in the alternative that the matter be remitted, or in the further alternative that the deletion order of 9 January 2015 be declared null and void. No responses were requested.

Main issue: Whether installation of the labyrinth rail constituted completion work that triggered the time limit, and whether the Cantonal Court established the facts arbitrarily.

Considerations

The decision refusing provisional registration is a final decision under Art. 90 FSCA; the admissibility requirements are met. Since decisions on the provisional registration of builder's liens are interim measures within the meaning of Art. 98 FSCA, only the violation of constitutional rights may be raised, and then under the strict complaint principle of Art. 106 para. 2 FSCA.

New evidence could not be considered under Art. 317 para. 1 CPC, since it was not shown why it could not have been submitted at first instance. The determinative file is the one as it was before the lower court.

Under Art. 839 para. 2 CC, registration must be made within four months of completion of the work. Construction work is deemed complete when all obligations under the contract for works have been performed. Minor work serving purely to perfect the work or to remedy defects does not fall within this, unless it is indispensable; the assessment is qualitative and not quantitative (BGE 125 III 113 E. 2b). Because of the purpose of the peremptory time limit, less strict requirements apply to the showing of prima facie evidence (BGE 137 III 563 E. 3.3). The Cantonal Court correctly presented this case law.

The arbitrariness complaint fails: the Cantonal Court assessed the documents on file comprehensively. The appellant itself stated in its final invoice of 29 September 2014 that 1 September 2014 was the last delivery and installation date. The acceptance record of 2 September 2014 described the installation of the labyrinth rail as an…