Facts
Subject: contract for work, performance of the contract; appeal against the judgment of the Civil Court II of the Cantonal Court of the Canton of Valais of 21 October 2015.
Parties: the appellant [X.] (owner of the work, plaintiff at first instance) and the respondent [Z. Sàrl] (contractor, defendant).
Main facts:
- On 20 March 2006, the parties concluded a "construction contract" for the design and then construction of a villa on a share of condominium ownership in the municipality of [S.] (VD). The price was CHF 915,531.70 (CHF 565,000 fixed price for the basic work and CHF 350,531.70 outside the fixed price for additional work). The SIA 118 standard (ed. 1977/1991) was incorporated into the contract. The specifications expressly excluded the seeding of terraces and landscaping work. The budget for earthworks was set at CHF 45,000.
- Work began in October 2005, before the contract was signed. The price was reduced to CHF 750,700.80 according to the estimate of 2 August 2006.
- On 8 December 2006, the contractor issued the final statement: a total of CHF 788,826.10, including CHF 59,477.45 for earthworks. After instalments of CHF 728,500, the balance due was CHF 60,326.10. The owner signed this statement.
- On 15 December 2006, the parties signed a minutes titled "Acceptance of the work" referring to Arts. 157 et seq. SIA 118. External fittings were noted as to be completed in spring. The box "The work is deemed accepted (Arts. 159 and 160)" and the box "No reservations are made by the owner" were ticked.
- In January 2007, the owner paid CHF 45,000. On 5 February 2007, the contractor demanded the balance of CHF 15,326.10.
- On 9 February 2007, the owner announced the sale of the villa for health reasons and made payment of the balance conditional on the removal of the listed defects: fitting a closing sleeve on the balustrade, adjusting a horizontal bar, and finishing the garden work. When questioned at first instance, the owner confirmed that these works were the only external fittings still to be carried out.
- The contractor demanded a payment guarantee. On 7 May 2007, the owner granted a mortgage note of CHF 16,000 in second rank. The contractor's manager stated at first instance that the external fittings had been completed after receipt of the mortgage note.
- On 5 October 2007, the contractor undertook towards potential purchasers to carry out certain works (levelling, topsoil, concrete plinths, fencing, seeding if possible).
- On 18 October 2007, the owner sold the plot for CHF 1,050,000, with an obligation to complete the external fittings no later than 30 November 2007. The transfer took place on 21 November 2007.
- On 12 February 2008, the contractor sent the purchasers two estimates ("Earthworks" of CHF 16,144.85 including VAT, and "External fittings" of CHF 20,218.35 including VAT). The purchasers' counsel then demanded completion of the works.
- On 14 and 17 July 2008, the owner entered into a settlement with the purchasers and acknowledged a debt of CHF 39,000 as a lump sum in full and final settlement.
Procedure: On 26 November 2008, the owner filed a claim before the District Court of Monthey, seeking CHF 39,000 as a price reduction (Arts. 169 to 171 SIA 118 and Art. 368 CO), as well as CHF 4,444 in pre-trial legal fees. The contractor sought dismissal of the claim. On 6 February 2014, the district judge dismissed the claim for lack of proven non-performance. On 21 October 2015, the Civil Court II upheld the dismissal, while finding that the contractor had breached its obligation to deliver a completed work; it nevertheless held that the owner had not proven the existence or extent of its loss. The owner abandoned the expert opinion because of the cost of the advance on costs.
Submissions before the Federal Supreme Court: the appellant requests recognition of the debt of CHF 39,000 with interest at 5% from 14 July 2008 and of CHF 4,444 with interest at 5% from 26 November 2008. The respondent requests dismissal of the appeal.
Considerations
1. Admissibility. The civil appeal is admissible: it was filed in time (Art. 100 para. 1 FSCA), by the party that fully lost (Art. 76 para. 1 FSCA), against a final decision (Art. 90 FSCA) rendered in civil matters (Art. 72 para. 1 FSCA) by a higher court sitting on appeal (Art. 75 FSCA), in a pecuniary matter exceeding CHF 30,000 (Art. 74 para. 1 let. b FSCA). The Federal Supreme Court relies on the facts established by the prior authority (Art. 105 para. 1 FSCA) and may depart from them only if those facts are manifestly incorrect (arbitrariness, Art. 9 Cst.) or were established in breach of the law (Art. 95 FSCA), with influence on the outcome of the case (Art. 97 para. 1 FSCA). It applies the law of its own motion (Art. 106 para. 1 FSCA) but is limited to the issues raised in the appeal (Art. 42 para. 2 FSCA).
2. Characterisation of the contract. The "construction contract" is characterised as a total contract for work. The total contractor undertakes to perform the work in place of the partial contractors, and in addition takes charge of preparing the designs and plans (ATF 114 II 53 consid. 2a; judgment 4A_99/2015). In casu, the contractor built the villa according to plans that it had itself prepared. The contract is therefore a contract for work within the meaning of Art. 363 CO (ATF 117 II 273 consid. 3a).
3. Contractual liability and delivery of the work. The appellant argues that the contractor incurred liability (Art. 97 para. 1 CO) for failing to complete the work, and that the loss corresponds to the CHF 39,000 paid to the purchasers, as proven by the estimates of 12 February 2008. The owner's duty to inspect and give notice arises upon delivery (Art. 367 para. 1 CO; ATF 117 II 264 consid. 2a), which presupposes completion of the works (ATF 118 II 142 consid. 4); for the contractor, acceptance corresponds to delivery (ATF 129 III 738 consid. 7.2). Delivery consists in handing over the work completed in accordance with the contract, regardless of whether defects exist (ATF 129 III 738; 115 II 456 consid. 4). It may result from a notice of completion, the receipt of which is sufficient (GAUCH, no. 98). This Court…