Facts

The appellant, an architect represented by a lawyer, submitted with the consent of the owner, on 24 June 2013, to the Municipality of X. an application for a development plan for a residential complex of nine contiguous and partially underground blocks, with 13 apartments, an underground garage for 48 parking spaces and a gross floor area of 2'491 m2, located on plots on a steep slope totaling 2'481 m2 in [Y.], an intensive residential zone subject to a development plan.

The plots fall within the federal ISOS inventory and the village of [Y.] has been listed in the federal IFP inventory since 1983. The project provides for glazed facades with sun screens, flat roofs, a south-east front about 78 m long, a block for a car lift about 12 m high and terraces supported by stone walls.

Neighbouring objectors (including C. and B.) opposed the project. The cantonal authority issued a negative preliminary opinion on the project on 26 March 2014, referring to the negative opinions of the Federal Commission for Nature and Landscape Protection and the cantonal services. The Municipality refused the permit on 18 September 2014. By decision of 19 August 2015 the Council of State confirmed the refusal, reducing the fee to CHF 3'000.--.

By judgment of 23 March 2017 the Administrative Court of the Canton of Ticino dismissed the appellant's appeal, finding the aesthetic assessments and the lack of harmonious integration into the landscape to be sustainable. The appellant brought an appeal before the Federal Supreme Court requesting annulment of the judgment and the issuance of the permit. No observations were requested on the appeal.

Considerations

The Federal Supreme Court in principle admits the admissibility of the public law appeal against the final decision of the last cantonal instance, and recognises the appellant's standing under Art. 89 para. 1 FSCA, having submitted the application with the owner's consent and participated in the cantonal proceedings.

As to the failure to conciliate, the Federal Supreme Court notes that Art. 23 para. 1 LPAmm and Art. 9 LE are optional in nature and do not require a conciliation attempt. The objections concerned the entire construction, considered too invasive from a landscape standpoint, so that a conciliation attempt was not manifestly likely to succeed. The complaint, examined under the arbitrariness standard, is therefore unfounded.

The appellant further complains that the cantonal opposition stated, in the alternative, that any construction would be invasive, amounting to a denial of buildability. The Federal Supreme Court notes that the complaint of insufficient reasoning was not raised as a violation of the right to be heard in compliance with Art. 106 para. 2 FSCA; the cantonal court had in any case clarified that the negative preliminary opinion concerned the invasiveness of the plan and not the buildability of the plots, which remain subject to the applicable building rules.

Regarding the alleged violation of municipal autonomy as a result of the binding cantonal preliminary opinion under Art. 7 para. 2 LE, the complaint is inadmissible for insufficient reasoning: the Municipality refused the permit also on the basis of Art. 20 para. 1 NAPR, and the principle of orderly and harmonious integration into the landscape under Art. 104 para. 2 LST is applicable by the cantonal authority under Art. 109 para. 2 let. c LST.

On the merits, the Federal Supreme Court observes that the development plan, according to Art. 54 and 55 LST, gives concrete form to objectives of landscape, architectural and urban quality and must already at that stage respect the architectural and landscape characteristics of the historic core under Art. 20 para. 2 NAPR. The project anticipated precise architectural details (facades, openings, external arrangement), so the aesthetic examination was not reserved to the building permit stage alone.

As to the aesthetic clause, case law requires, for a refusal based on it to be justified despite compliance with the building parameters, a預 prevailing…