Facts

The dispute concerns a building permit for the reconstruction and extension of a farm building in an agricultural zone, following the destruction by fire in January 2015 of the residential and farm building located on parcel no. 107 of the Commune of Vulliens (VD). The owner, [C.] (the respondent and builder), operates an agricultural business with 135 head of livestock (100 LSU) and 9'000 laying hens (90 LSU).

Considerations

The public law appeal is admissible (art. 82 let. a, 86 para. 1 let. d, 89 para. 1 FSCA) against a final decision of the last cantonal instance in building law matters. The Federal Supreme Court is bound by the cantonal findings of fact, as the appellants have not shown arbitrariness (art. 97 para. 1 FSCA) or that a correction would affect the outcome of the case. Taking the slope into account, which is not alpine, is a matter of assessment and does not constitute a manifestly incorrect finding of fact.

On the right to be heard (art. 29 para. 2 Cst.), the refusal of an inquiry within the meaning of art. 2 para. 5 let. b OAPC and the hearing of witnesses do not violate this right. In the context of pre-existing nuisances and of the authorisation procedure, the objections of neighbours are sufficient to establish the alleged annoyance, and a further inquiry would not make it possible to conclude that a significant part of the population is disturbed (within the meaning of the threshold of 25% and at least twenty responses in FAT report no. 476).

On spatial planning (art. 16a SPA, 34 SPO, art. 22 para. 2 let. a SPA), reconstruction on the same site is permitted: the guarantee of the acquired situation applies to the farm building destroyed by force majeure, a fortiori as compared with a non-agricultural building (art. 42a para. 3 SPO). For the extension, the needs clause and the weighing of interests (art. 34 para. 4 let. b SPO, principle of concentration) must be respected. The Federal Supreme Court shows restraint as to the assessment of heritage protection: the distance recommended by the master plan is not a mandatory rule, the surroundings of the church are not free of construction, and conditions for the treatment of the façades are imposed; the specialist service deferred to the planning service. The prevalence of measured land use, the rationalisation of the operation and the entry in the land register requiring dismantling justify the extension.

On odour protection distances (art. 11 para. 2 EPA, ch. 512 annex 2 OAPC, FAT report no. 476 of 1996 and the 2005 draft withdrawn but usable as a reference), the correction factor of 1.0 is justified: the factor of 1.2 targets marked slopes, particularly in alpine areas, the correction linked to altitude being unrelated to slope. The gradient of the terrain, which is established but slight, does not justify a factor of 1.2, as the FOEN confirmed. The 30% reduction for mixed zones (ch. 2.3 of the FAT report) remains in the 2005 draft (reduced to 50% in agricultural zones) and may be confirmed in view of the situation of dwellings bordering the agricultural zone.

On excessive immissions (art. 11 para. 3 EPA, art. 2 para. 5 let. b and art. 5 OAPC), the active measures (ventilation, management of slurry removal according to the weather and weekdays) and passive measures (maintained vegetation screen, additional tree planting) imposed by the DGE are sufficient at the building permit stage. Should excessive nuisances arise, art. 9 OAPC would allow intervention.

On the arbitrariness complaint concerning the modified composition of the municipal council (Art. 83 FSCA, art. 9 Cst.), the cantonal court could consider that the new decision of 22 July 2016 constituted a decision on the recusal request and that the complaints directed against the councillors of the second decision, not raised in due time (art. 10 para. 2…