Facts

Parties and context. The appellants [A.] Corporation and [B.] Company, companies based in Cairo and owned by the State of Egypt, active in the trade of oil and natural gas, operate the Arab Gas Pipeline. Respondent 1, [X.] , a company governed by Egyptian private law, acts as an intermediary between [B.] and Israeli buyers. Respondent 2, [Y.] Corporation Ltd, a company governed by Israeli law owned by the State of Israel, produces and markets almost all of the electricity in Israel.

Contracts. Within the framework of the Gas for Peace Deal, three contracts were concluded: the Gas Supply and Purchase Agreement (GSPA) of 13 June 2005 between [B.] and [X.] , governed by English law, with a CRCICA arbitration clause seated in Cairo (arts. 14.2, 14.9 and 14.10 of Annex 1); the On-Sale Agreement of 8 August 2005 between [X.] and [Y.] , with an ICC arbitration clause seated in Geneva (art. 10.2); and the Tripartite Agreement of 13 June 2005 between [B.] , [X.] and [Y.] , Annex 6 to the GSPA, with an ICC arbitration clause in Geneva (art. 9) and a promise of delivery of 2.2 BCM per year (art. 1). Art. 14.10 of Annex 1 to the GSPA requires CRCICA arbitration in Cairo for disputes between [B.] and [X.] arising from the Tripartite Agreement where [Y.] is not a party to the dispute.

Performance facts. Delivery delays occurred. After the Arab Spring, thirteen terrorist attacks targeted the pipeline between 5 February 2011 and 9 April 2012. [B.] terminated the GSPA on 18 April 2012, [X.] terminated on 9 May 2012, and [Y.] noted on 6 February 2013 the extinction of the Tripartite Agreement.

Arbitral proceedings. On 6 October 2011, [X.] filed an ICC arbitration request against [B.] and [Y.] . The ICC arbitral tribunal, seated in Geneva, rendered on 4 December 2015 a 469-page award: it declared itself without jurisdiction over the claims based on the GSPA, but competent over those based on the Tripartite Agreement. It awarded [X.] USD 230,935,579 for the unjustified termination and USD 57,357,135 for the defective deliveries, and [Y.] USD 1,650,564,941 and USD 113,092,525. A decision of 15 March 2016 dismissed the requests for correction. A parallel CRCICA procedure resulted in a partial award of 11 November 2013 accepting the jurisdiction of the Cairo tribunal.

Appeal. On 19 January 2016, [A.] and [B.] lodged a civil appeal (art. 190 para. 2 let. b and d PILA) seeking the partial annulment of the award and a finding that the arbitral tribunal lacked jurisdiction over the claims arising from the Tripartite Agreement. The respondents requested dismissal. The arbitral tribunal did not submit observations. The arbitral awards produced on 19 April 2017 by the counsel of [X.] were declared inadmissible as new exhibits (art. 99 para. 1 FSCA).

Language. The Federal Supreme Court drafted its judgment in French, the language of the appeal (art. 54 para. 1 FSCA, art. 42 para. 1 FSCA, art. 70 para. 1 Cst.).

Considerations

Admissibility. The civil appeal is admissible against an international arbitral award under the conditions of arts. 190 to 192 PILA (art. 77 para. 1 let. a FSCA). The appeal must satisfy the requirement of reasoning in art. 77 para. 3 FSCA in connection with art. 42 para. 2 FSCA; references to the arbitral submissions and new arguments presented in reply are inadmissible (art. 100 para. 1 FSCA). The Federal Supreme Court rules on the basis of the facts established in the award (art. 105 para. 1 FSCA) and does not review the facts beyond the admitted exceptions. The new exhibits produced on 19 April 2017 are set aside (arts. 99 para. 1 and 105 para. 1 FSCA).

Jurisdiction (art. 190 para. 2 let. b PILA). The Federal Supreme Court freely examines the question of jurisdiction, including preliminary questions. The arbitral tribunal had held that [X.] was the beneficiary of the promise of delivery contained in art. 1 of the Tripartite Agreement. The Federal Supreme Court confirms this interpretation: the mention “to [Y.] ” designates the recipient of the gas and not the sole beneficiary of the promise; the signature of [X.] and art. 10 of the contract imply that it acquired rights; a trilateral structure aimed to create a single forum for tripartite disputes; the preamble and art. 14.10 of the GSPA confirm this reading. The entitlement to a claim based on the Tripartite Agreement constitutes a condition of jurisdiction of the ICC tribunal, and not a mere question of merits, so that the question falls within jurisdiction ratione materiae. English law, chosen in art. 9 of the Tripartite Agreement, governs the interpretation of the substantive clause; art. 178 para. 2 PILA, relating solely to the arbitration agreement, does not entail the alternative application of Swiss law to this clause. The six arguments of the appellants are set aside: the text is not clear in their favour, the incorporation theory is not refuted, the absence of consideration under English law is contradicted by the award, the option of jurisdiction is not incompatible with the clauses, and the cumulation of proceedings results from the appellants' own initiative. The subsidiary argument based on art. 14.10 of the GSPA is admissible as it was raised before the arbitral tribunal; it fails because [Y.] was a party to the dispute, the arbitration clause being satisfied by its claims, even if later abandoned.

Right to be heard (art. 190 para. 2 let. d PILA), force majeure. The arbitral tribunal has a minimum duty to examine the relevant…