Facts
The appellant [A.] is the owner of the undeveloped parcels Nos. 1739 (2,703 m2) and 1742 (2,068 m2) located in residential zone B in the municipality of Flims. The parcels lie on the edge of the settlement but are largely surrounded by existing buildings.
Between October 2012 and November 2012 the appellant submitted five building applications to the municipality of Flims: 2012-0110 (underground garage on parcels 1739 and 1742), 2012-0111 (multi-family house B), 2012-0112 (multi-family house C on parcel 1739), 2012-0121 (multi-family house A on parcel 1742) and 2012-0128 (single-family house on parcel 1739). All applications were published. Neighbours and Helvetia Nostra filed objections against all applications.
By decision of 9 December 2014 the Municipal Executive Board of Flims partially upheld the objections and dismissed all five building applications. The procedural costs of CHF 25,169.70 were imposed on the appellant. The Administrative Court of the Canton of Graubünden (5th Chamber) dismissed the appeal on 1 September 2015.
By way of a public law appeal, the appellant requested that the administrative court judgment be set aside, in particular the annulment of the joinder of the five proceedings and an individual assessment of the applications in chronological order. In the alternative, the matter be remitted in accordance with the considerations. The counterparties and the Administrative Court requested dismissal; the municipality of Flims and Helvetia Nostra likewise, insofar as the appeal is admissible. During the proceedings, on 8 April 2016 the appellant submitted an alternative building application for a single-family house with an annex apartment on parcel 1739; the municipality suspended the proceedings on 10 May 2016. The appellant declared that this was not a withdrawal of the appeal.
In dispute was in particular the violation of Art. 29 para. 2 Cst. and Art. 6 no. 1 ECHR due to the joinder of the proceedings not having been ordered by a procedural decision, as well as the countability of sauna areas (approx. 182.4 m2) and accesses/stairwells (approx. 82.17 m2) as countable floor area. The Administrative Court found that the building projects exceeded the permissible utilisation by more than 200 m2.
Considerations
The appeal is admissible as a public law appeal against a final cantonal decision of last instance (Art. 82 ff., Art. 90, Art. 95 lit. a FSCA). The appellant, as addressee and landowner, is entitled to challenge the decision.
As to the complaint of violation of the right to be heard (Art. 29 para. 2 Cst., Art. 6 no. 1 ECHR) due to the joinder of the building permit proceedings only in the decision of 9 December 2014 rather than by a procedural order pursuant to Art. 6 para. 1 lit. a VRG GR: the joinder was objectively warranted, as the five applications were submitted within a short period, were closely related and in part depended on one another. The joinder has neither substantive nor procedural legal effects and does not impair the procedural rights of the applicant. The amount of the fees remains unchanged, so a legal interest in challenging the joinder would be doubtful. The appellant could at any time amend, withdraw or suspend her applications until conclusion. No serious procedural defect exists; whether Art. 6 VRG was violated need not be examined (Art. 95 FSCA e contrario). Since the proceedings were ready for decision, the Municipal Executive Board was entitled to conclude them in a single decision. The complaint is unfounded.
On the merits: the countability of the saunas as floor area was examined under Art. 37 para. 1 and para. 2 lit. g of the municipal building act. Decisive is the objective suitability of a room for residential use, not the subjective intention of the builder. The disputed…