Facts
Parties and courts: The appellant, the Communauté des propriétaires par étages Résidence X. (hereinafter: the community or the defendant), represented by a lawyer, opposes the respondent, Z. SA (hereinafter: the contractor or the plaintiff), represented by a lawyer. The case concerns an appeal in civil matters against the judgment of the Civil Court of Appeal of the Vaud Cantonal Court of 13 June 2016.
Background: The community wished to renovate the facades of its buildings located at chemin... à... (VD). In 2011, the contractor drew up an estimate dated 5 July 2011 for a total amount of CHF 360'013.40 incl. VAT, of which CHF 244'569.30 excl. VAT related to rendering and painting. This estimate included an item for chipping away spalled concrete, derusting the reinforcing bars and treating them, designated as an « estimate » of 67.50 hours at CHF 90.90, as well as lump-sum supplies of CHF 1'200.
Award: An EPF-trained architect appointed by the community found the estimate to be better prepared. At the general meeting of 10 November 2011, the contractor presented its offer. Following negotiations between the community's administrator and the contractor's managing director, the amount was reduced to CHF 350'000 net incl. VAT. The construction contract was concluded on 16 December 2011, with special conditions providing for payment of 90% during the works, the balance upon completion, and a 10% retention for 2 years.
Performance: The works began in February 2012. The contractor discovered significant rust on the reinforcing bars, which had not been anticipated in the estimate. It devoted 176 hours and then 216 hours of work to this item, with supplies of CHF 1'844.30 and then CHF 1'442.80. Daily time-and-materials vouchers, specifying the hours worked, were handed to the community's administrator. A supplementary estimate of CHF 6'958.50 concerning expansion joints was accepted on 7 March 2012. A supplementary invoice of CHF 14'406.95 was subsequently issued. The community paid CHF 364'406.75 in total. The works were completed on 27 June 2012.
Final statement and dispute: On 24 September 2012, the contractor drew up a final statement of CHF 411'239.80, claiming a balance of CHF 46'833.05. The community disputed this statement on 16 November 2012.
First instance proceedings: Seized on 14 February 2013 by the contractor, the Civil Court of the La Côte district appointed a judicial expert, who concluded that the concrete remediation works were in principle not agreed as a lump sum and that a time-and-materials price had been agreed for this item, without being able to definitively resolve the question of a partial lump sum. According to the expert, the invoiceable balance amounted to CHF 39'240.65. The judgment of 26 February 2015 ordered the community to pay only CHF 7'808, finding a partial lump-sum with reinforcing bar works invoiceable on a time-and-materials basis.
Appeal: The contractor appealed, maintaining its claims reduced to CHF 39'240.65 with interest at 5% from 1 November 2012. The Civil Court of Appeal allowed the appeal and ordered the community to pay CHF 39'240.65 with interest at 5% from 1 December 2012, the cantonal court finding that the first-instance judges had misread the expert's calculation. A rectification of 11 July 2016 fixed at CHF 16'925 the amount due for the reimbursement of advances on costs and first-instance costs.
Appeal to the Federal Supreme Court: The community lodged an appeal in civil matters, seeking primarily confirmation of the first-instance judgment, in the alternative a claim of CHF 8'740 or CHF 37'154.15, and in the further alternative annulment of the judgment. The contractor sought dismissal of the appeal.
Considerations
Admissibility: The appeal in civil matters is admissible. It was lodged in time by the party that lost (art. 48 para. 1, 76 para. 1, 100 para. 1 FSCA), against a final decision (art. 90 FSCA) rendered in civil matters (art. 72 para. 1 FSCA) by a superior cantonal court ruling on appeal (art. 75 FSCA), and in a matter whose amount in dispute exceeds CHF 30'000 (art. 74 para. 1 let. b FSCA). The Federal Supreme Court applies the law of its own motion (art. 106 para. 1 FSCA) and is bound by the findings of fact (art. 105 para. 1 FSCA), save for arbitrariness (art. 97 para. 1 FSCA). The dispute concerns only the remuneration for the remediation works on the reinforcing bars, the co-ownership having the capacity to sue for the common parts (ATF 142 III 551 consid. 2.2).
Establishment of facts and subjective interpretation: The appellant argues that the parties' real intention was to conclude a global lump sum of CHF 350'000 also covering the reinforcing bars. According to case law, the judge must first seek the real and common intention of the parties, based on indicia such as statements, context and subsequent conduct (ATF 132 III 268 consid. 2.3.2; ATF 118 II 365 consid. 1). This assessment is a question of fact and may only be reviewed under the angle of arbitrariness. The burden of proving a subjective intention lies with the party relying on it. The Federal Supreme Court finds that the cantonal court established, without arbitrariness, the existence of a real intention to agree an actual price for the reinforcing bars, on the basis of the expert report, the estimate (reference to « estimate »), the contractual documents and the time-and-materials vouchers. The contractor's conciliation request, the final statement mentioning supplementary works on the reinforcing bars, and the witness statements (interested or nuanced) do not demonstrate arbitrariness. The complaints based on art. 97 FSCA, art. 29 para. 2 Cst., art. 239 para. 2 CPC, art. 112 FSCA and art. 55 CPC are dismissed. Art. 319 para. 2 CPC does not exist, so its alleged violation cannot be invoked.
Partial lump sum and art. 373 CO: Under art. 373 CO, the lump-sum price binds the contractor as well as the client, save for extraordinary circumstances (art. 373 para. 2 CO). By contrast, where the parties agree on…