Facts
The [C. GmbH] (now in liquidation, respondent 2) supplied the [A. GmbH] (appellant) with kitchen natural stone worktops and on 4 April 2014 demanded CHF 42'687.35. After the claim was assigned to its managing director [B.] (respondent 1), he sued before the Höfe District Court. The appellant filed a counterclaim based on unperformed contracts for work and materials and later declared set-off against a kitchen installation in the amount of CHF 21'880.95.
By judgment of 6 June 2016, the Höfe District Court ordered the appellant to pay CHF 38'166.60 plus interest, set aside the objection to the payment order and granted definitive debt enforcement relief. It dismissed the counterclaim. By judgment of 13 June 2017, the Schwyz Cantonal Court dismissed the appellant's appeal, insofar as it entered into it.
The appellant filed a civil law appeal with the Federal Supreme Court, requesting that the lower court's judgment be set aside, the action be dismissed and the counterclaim be upheld in the amount of CHF 32'144.75. Respondent 1 requested that the appeal be dismissed; respondent 2 did not submit a response. Suspensive effect was granted.
The disputed issues were in particular: (1) whether there was an aliud (wrong delivery), (2) whether the defect notice was timely and sufficient, (3) whether an intentional defective delivery is admissible as a new submission, (4) whether the set-off declaration of 29 January 2016 was late and (5) whether a double payment in the appeal proceedings is to be regarded as a novum.
Considerations
The Federal Supreme Court bases its decision on the facts established by the lower court (Art. 105 para. 1 FSCA) and may only correct them if they are obviously incorrect (arbitrary) and correction of the defect may be decisive (Art. 105 para. 2, Art. 97 para. 1 FSCA). The appellant must clearly and substantiatedly show how these requirements are met. In addition, the appeal must address the reasoning of the contested decision in a targeted manner (Art. 42 para. 2 FSCA); mere reference to earlier written submissions is not sufficient. Where a decision rests on several independent grounds, each must be challenged. On this basis, the complaints against the main reasoning regarding the showroom kitchen are inadmissible (consid. 2.3).
An aliud exists where the contractor delivers not the work owed but another work; it is then a wrong delivery and not a defective delivery within the meaning of the warranty for material defects under Art. 367 et seq. CO. The lower court denied an aliud because the type of stone was not essential for a kitchen worktop. The appellant only asserted general quality differences and did not demonstrate which specific contractual agreements made the delivered stone appear to be an aliud. There is therefore no violation of federal law (consid. 3.1).
The duty to examine and give notice of defects under Art. 367 para. 1 CO requires the customer to inspect the condition of the work as soon as this is feasible in the ordinary course of business and to inform the contractor without delay. The mere request for an expert opinion does not release the customer from the duty of examination and of timely notice. A defect notice given to the court in the statement of defence is not sufficient in the present case, as it was late; the question of its fundamental admissibility could be left open. Rescission is excluded due to the breach of these duties (consid. 3.2).
The assertion of an intentional defective delivery (Art. 370 para. 1 CO) was rightly qualified in the appeal proceedings as new within the meaning of Art. 317 para. 1 CPC, because the rejoinder did not disclose who had treated the granite and that this served to conceal the defect. The appellant did not argue that the requirements of Art. 317 para. 1 CPC were met (consid. 3.3). An offer of witness evidence is only compliant with form if it can be…