Facts
Parties and proceedings: The appellant, [A.] , direct neighbour (owner of adjoining parcels 305 and 2223), is represented by a lawyer. The respondent, [B. SA] , is a real estate company owning parcel 1618 of the Commune of Leysin and acts as the builder. The Commune of Leysin (Municipality) also intervenes. The case concerns a building permit and follows a judgment of the Court of Administrative and Public Law of the Vaud Cantonal Tribunal of 29 January 2016.
Subject matter: building permit, lapse and extension, revocation of an unlawful extension decision.
Chronology
- On 22 December 2011, a building permit was issued for a chalet, and on 1 February 2012, for a building of nine apartments.
- On 14 October 2013, the Municipality extended these permits at the builder's request, expressly citing the provision of the LATC relating to lapse and extension.
- On 20 November 2014, the Municipality accepted, "on an exceptional basis", a further one-year extension, although the legal possibilities of extension had been exhausted.
- On 13 March 2015, following an intervention by the appellant, the Municipality found that the permits had definitively lapsed (maximum validity of three years).
- On 23 July 2015, the Municipality maintained its position. The builder appealed to the Court of Administrative and Public Law, which annulled the municipal decisions and held that the permits remained valid until 31 January 2016.
Appeal to the Federal Supreme Court: the appellant requests the annulment of the cantonal judgment and of the decision of 20 November 2014. The Cantonal Tribunal concludes to dismissal, the Municipality defers to the court, and the respondent concludes to dismissal.
Grounds: (1) nullity of the extension decision; (2) revocation of the extension, on the ground that the permits no longer comply with art. 75b Cst. since its adoption.
Considerations
Admissibility and statement of facts: The public law appeal is admissible (art. 82 let. a, 86 para. 1 let. d and 90 FSCA). The appellant, as direct neighbour, is particularly affected and has an interest worthy of protection. The Federal Supreme Court does not take into account the appellant's version of the facts, absent a demonstration of a manifestly incorrect finding of fact (art. 95 and 97 para. 1 FSCA). The missing documents invoked in the reply are not taken into consideration, as the appellant did not unsuccessfully request their production and does not invoke any violation of the right to be heard; no new facts or evidence are admissible (art. 99 para. 1 FSCA).
Unlawfulness of the extension: According to art. 118 LATC, the permit lapses if construction has not begun within two years; the municipality may extend it by one year if circumstances justify it. It is undisputed that the extension of 20 November 2014 violates this provision and is unlawful.
Nullity: Absolute nullity only attaches to the most serious defects, which are manifest or easily detectable, and only if legal certainty is not seriously endangered (ATF 138 II 501; ATF 138 III 49; ATF 137 I 273). Only serious procedural defects or a qualified lack of competence justify it. In the present case, the initial permits were issued regularly and in accordance with substantive law; the error consists only of a further extension, which does not constitute a serious defect. The nullity ground is dismissed.
Revocation and balancing of interests: A unilateral act may be amended or revoked by the authority to restore compliance with the law, without an express legal basis (ATF 103 Ib 204). In the absence of a positive rule, a balancing must be carried out between the interest in the correct application of the law and the interest in legal certainty and the protection of legitimate expectations (ATF 137 I 69; ATF 135 V 215; ATF 127 II 306). Relevant factors include the creation of a subjective right, the use already made of the authorisation, the thoroughness of the procedure and the good faith of the administered party; a person who has misled the administration cannot in principle oppose revocation, unless it is disproportionate (ATF 98 Ib 241; ATF 93 I 390).
Scope of art. 75b Cst.: Adopted on 11 March 2012 and directly applicable (ATF 139 II 243), it limits second homes to 20% of the housing stock. Only the date of issue of the authorisation is decisive (ATF 139 II 243), so that the provision never entails the revocation of validly granted permits. Its impact on the extension falls within cantonal…