Facts

The appellant [A. SA] is a company engaged in the processing of aggregates and in the production of concrete. It owns the parcel yyy in [X.] , located outside the building zone, and also carries out its activity on other neighbouring parcels in the same zone.

During works to modify the aggregate processing/crushing plant, a neighbour who co-owns nearby parcels ([B.] ) asked the Municipality of [X.] to order the immediate suspension of the works and to verify their scope, subsequently requesting that a building permit application be imposed. On 5 February 2014 the Municipality rejected this latter request, considering that the works were mere maintenance interventions not subject to a building permit.

Seized by the neighbour, on 8 July 2014 the Council of State of the Canton of Ticino partially upheld the appeal, requiring the Municipality to order the filing of a retrospective building permit application for the works carried out. By judgment of 15 June 2015 the Administrative Court of the Canton of Ticino dismissed the company's appeal.

By way of a public law appeal to the Federal Supreme Court, the company requests, as its main claim, the annulment of the cantonal decision and a finding that no building permit application is necessary; in the alternative, it requests that the case be remitted to the cantonal court to carry out an on-site inspection. No observations on the appeal were requested.

The Federal Supreme Court, examining admissibility of its own motion, found that the contested decision is not a final decision but an interlocutory ruling within the meaning of Art. 93 FSCA, as it refers to the Municipality the determination of whether the works require a building permit and whether such permit may be granted.

Considerations

The Federal Supreme Court notes that the contested decision does not conclude the proceedings, as it confirms the Municipality's obligation to order a retrospective building permit application and leaves to the municipal authority the task of establishing, through a preliminary review, whether the works require a permit and whether such permit may be granted, taking into account environmental impacts (noise and air). It is therefore an interlocutory ruling within the meaning of Art. 93 FSCA, essentially a remittal decision, with respect to which the Municipality retains a certain margin of assessment.

Under Art. 93 para. 1 FSCA, an appeal against an interlocutory decision is admissible only if it may cause an irreparable harm (let. a) or if upholding the appeal would immediately result in a final decision, avoiding a lengthy or costly evidentiary procedure (let. b). The burden of demonstrating these requirements lies in principle with the appellant, unless they are manifest. Mere prolongation of the proceedings or increased costs are generally not sufficient; a legal harm is required.

As regards irreparable harm, the Federal Supreme Court finds that the appellant has not expressed itself adequately. The mere obligation to file a building permit application does not in itself constitute irreparable harm. Moreover, the neighbour's request for interim measures became moot with the cantonal government's decision of 8 July 2014, so the appellant may continue to use the installations until the outcome of the municipal verifications. The argument that the request for a building permit…