Facts

[H. AG] (building owner) submitted a building application on 21 January 2014 to the Ennetbürgen Municipal Council (building authority) for the construction of two multi-family houses on a steeply sloping plot No. 783, whereby the houses in the rear area were to be built into the rock.

The neighbours [A.] , B. and C. [D.] and the heirs' community [E.] ([F.] and [G.] ) lodged objections, as they feared that the safety of their properties would be endangered by the cut into the slope or rock removal required for the construction. After amended plans (flood protection) and statements from the cantonal offices, the neighbours did not respond within the period extended until 30 June 2014.

By decision of 3 July 2014, the Municipal Council dismissed the objection and granted the building permit. According to point 1, the excavation of the construction pit is excluded from the permit and must be applied for separately; point 5.6 requires the rock removal concept to be submitted for approval at least 6 weeks before the start of construction, approval by the Technical Commission for a geotechnical report, and confirmation of the removal method by a geologist.

The neighbours lodged an administrative appeal with the Nidwalden Regierungsrat (dismissed on 24 February 2015) and subsequently an administrative court appeal with the Nidwalden Administrative Court, which was dismissed by decision of 31 August 2015. The Administrative Court proceeded on the basis that the excavation of the construction pit was included in the building permit and that the missing concept submission could be remedied as a minor defect within the meaning of Art. 226 para. 2 BauG by means of an ancillary provision.

By public law appeal, the neighbours applied to the Federal Supreme Court for the annulment of the lower court's decision and the refusal of the building permit. The Regierungsrat requested dismissal, as did the building owner; the municipality waived its right to comment.

The subject matter of the dispute is whether the excavation of the construction pit or the rock removal concept requires a separate permit and whether the lower court's decision is a challengeable final decision or an interlocutory decision.

Considerations

The Federal Supreme Court examines of its own motion the admissibility of the appeal (Art. 29 para. 1 FSCA). An appeal in public law matters is in principle available against a final cantonal decision in building law, and the neighbours are entitled to appeal as owners of adjacent properties (Art. 86 para. 1 FSCA). It is doubtful, however, whether a final decision within the meaning of Art. 90 FSCA exists.

The Administrative Court proceeded on the basis that the excavation of the construction pit was covered by the building permit; the wording in point 1 was admittedly misleading but is clearly recognisable from point 5.6. The Federal Supreme Court does not follow this interpretation: point 1 expressly excludes the construction excavation and requires a separate application, and point 5.6 requires separate permission for the rock removal concept by the Municipal Council as well as approval by the Technical Commission. Excavation work may not begin before this permission, which is therefore a condition for the practical effectiveness of the building permit.

According to case law, building permit proceedings are not regarded as concluded as long as no decision has been taken on such a condition and the authority still has a margin of discretion in assessing it. In the present case, the municipality retains considerable discretion, as it remains open whether purely hammer-based removal or blasting may exceptionally be permitted and which safety measures are to be ordered. The contested decision…