Facts
Subject matter and procedure: civil law appeal filed by the appellant trading company ([X. SA] , subject to Panamanian law) against the final award rendered on 12 May 2015 by an ad hoc arbitral tribunal in an international arbitration. The respondents are [Y.] (a company governed by Liechtenstein law, controlled by [Z.] ) and [Z.] Company (a company governed by Iranian law). The appellant seeks annulment of paragraphs 4 and 6 of the operative part of the award, alleging breach of its right to be heard (art. 190 para. 2 let. d PILA). A request for provisional measures was rendered moot by an addendum of 9 September 2015.
Contractual background: in 1968, the State of Israel and [Z.] concluded a participation agreement for the construction and operation of a pipeline linking Eilat to Ashkelon. In 1969, [Y.] and [X.] created [D.] Co Ltd, whose agreement contains an arbitration clause fixing the seat of arbitration in Zurich. In 1978, [Z.] and [D.] concluded a contract for the delivery of approximately 14.75 million tonnes of Iranian oil to [X.] (the 1978 contract).
Arbitral proceedings: on 13 January 1989, [Y.] filed a request for arbitration claiming USD 445,336,076.36 for 50 unpaid deliveries made from September to December 1978. A partial award of 17 June 2003 upheld this claim, reserving the interest and the counterclaims of [X.] . The latter filed a counterclaim in 2004 concerning three heads: the 1978 shortfall (approximately 2.9 million tonnes not delivered following the political events in Iran), the alleged breach of a 1979 contract, and the obligation to conclude supply contracts until 2017. After the close of the hearings, a closing hearing (November 2007) and supplementary questions, the president of the arbitral tribunal died in November 2012 and was replaced in February 2013. The new tribunal refused, by order of 26 September 2013, the holding of an additional hearing requested by the appellant. The delay in drafting the award was noted by the president.
Operative part of the award of 12 May 2015 (by majority): the tribunal declined jurisdiction with respect to [D.] , accepted jurisdiction with respect to [Z.] , ordered [X.] to pay USD 445,336,076 plus interest to [Z.] and [Y.] (joint creditors), held [Z.] and [Y.] jointly liable to [X.] up to USD 99,455,767 plus interest for the 1978 shortfall, ordered set-off, and then ordered [X.] to pay [Z.] USD 1,123,709,315 with LIBOR interest. The arbitrator appointed by the appellant issued a dissenting opinion, annexed to the notification.
Submissions before the Federal Supreme Court: the response of the president of the arbitral tribunal (9 March 2016) implicitly concludes for dismissal. The respondents conclude that the appeal is inadmissible or, alternatively, that it be dismissed, and request payment of the security of CHF 250,000 provided by the appellant. The reply (1 April 2016) requests that the president's submission be declared inadmissible and that all procedural orders be transmitted; the rejoinder (18 April 2016) waives further development of the arguments.
Considerations
Language and admissibility: the judgment is drafted in French, the language chosen by the parties, the award being in English (art. 54 para. 1 FSCA). The civil law appeal in international arbitration is admissible under the conditions of arts. 190 to 192 PILA (art. 77 para. 1 FSCA); no admissibility condition poses a problem.
Dissenting opinion and the president's submission: a dissenting opinion is not part of the award and has no independent legal effect; it therefore may not be taken into consideration. As for the president of the arbitral tribunal's submission of 9 March 2015, presented in a personal capacity and not on behalf of the majority, it does not represent the view of the panel; it is not decisive and will be disregarded, as will the remarks of the reply that relate to it. New arguments presented in the reply cannot supplement a late statement of reasons (art. 100 para. 1 FSCA in conjunction with art. 47 para. 1 FSCA). The request to transmit all procedural orders is dismissed, the Court considering itself able to rule.
Establishment of the facts: the Federal Supreme Court relies on the facts established in the award (art. 105 para. 1 FSCA, art. 77 para. 2 FSCA), unless a ground under art. 190 para. 2 PILA is raised against them or new facts or means of evidence may exceptionally be taken into consideration.
Right to be heard (art. 190 para. 2 let. d PILA): in Switzerland, the right to be heard relates essentially to the establishment of the facts. The right to be consulted on legal questions is limited (iura novit curia): a prior consultation is required only exceptionally, where the tribunal intends to base its decision on a legal norm or legal consideration not raised and whose relevance the parties could not have anticipated. The notion of unforeseeability is interpreted restrictively, so as to prevent the argument of surprise from being used to obtain a substantive review of the award. The right to be heard does not require arbitrators to consult the parties on the scope of each exhibit, the principle of free evaluation of evidence being a pillar of international arbitration.
First limb: alleged contradiction regarding the date of breach: the appellant reproaches the tribunal for having fixed the damages as of 5 March 1979 while holding that the repudiation occurred on 28 June 1979, without having invited it to comment on a calculation based on a delivery subsequent to the breach. The Federal Supreme Court notes that the appellant simplifies or distorts the arbitral reasoning, which refers to “at latest” for 28 June 1979. Any possible contradiction is immaterial and would not suffice to found a public policy ground (art. 190 para. 2 let. e PILA). Only the unforeseeable character matters, and it is absent: the respondents show that the reasoning rests on the appellant's own assertions, which had itself placed the definitive refusal of delivery on 28 June 1979. Examining several possible dates in a complex and long-running case is nothing unusual. The complaint is dismissed.
S…