Facts

The co-owners of a parcel in Trimmis (Municipality of Trimmis, Canton of Graubünden) wanted to develop their parcel No. 664. In 2005 they concluded with the owner of the neighbouring parcels an easement agreement granting a right of way on foot and by vehicle, and in 2013 they submitted a building application for an access road that was to extend the Amselweg. After the municipality pointed out that the radius of the junction was insufficient, they submitted an amended building application in 2014. The Building Commission granted the building permit after dismissing the objections of four neighbours. The Municipal Executive dismissed the appeal on 10 November 2014.

The Administrative Court of the Canton of Graubünden partially upheld the neighbours' appeal on 12 May 2015, set aside the decision of the Municipal Executive and remitted the matter to the municipality for reassessment. It held that the development of parcels Nos. 663 and 664 should have been mandatorily entered in the General Development Plan pursuant to Art. 45 para. 1 CRA.

The Municipality of Trimmis lodged a public law appeal with the Federal Supreme Court. It requested that the Administrative Court's judgment be set aside and that the matter be remitted for consideration of the complaints not yet addressed (insufficient capacity of the Amselweg). In the alternative, it requested that the reassessment should not necessarily follow a legally binding amended General Development Plan, but could be based on planning at the level of a General Development Plan, a site plan or a quarter plan, as the municipality saw fit. The municipality complained in particular of a violation of its municipal autonomy. The neighbours primarily requested that the appeal be declared inadmissible and alternatively that it be dismissed.

The subject matter before the Federal Supreme Court was whether the municipality has autonomy when including the road-based fine development in the General Development Plan.

Considerations

The Federal Supreme Court considered the judgment of the Administrative Court to be a final cantonal decision in public law matters (Art. 82 let. a, Art. 86 para. 1 let. d FSCA). It classified the remittal decision as an interlocutory decision within the meaning of Art. 93 FSCA. An irreparable disadvantage (Art. 93 para. 1 let. a FSCA) existed, since a municipality could not reasonably be expected to appeal against its own revision of a land-use plan; the mere instruction to revise already caused such a disadvantage. The municipality, as a holder of sovereign authority, had standing to complain of a violation of its autonomy (Art. 89 para. 2 let. c FSCA). The appeal was therefore admitted.

Pursuant to Art. 50 para. 1 Cst., municipal autonomy is guaranteed within the limits set by cantonal law. A municipality is autonomous in a subject area if cantonal law does not regulate that area exhaustively and grants the municipality a relatively substantial freedom of decision. The sphere of autonomy may also concern a margin of discretion in applying cantonal or federal law. A discretionary decision or an indeterminate legal concept alone is not sufficient; the margin must be geared to the particular circumstances and needs of the municipalities. Autonomy is in particular weighed against where the margin serves a decision tailored to the individual case, where uniformity within the canton is intended, or where a conflict of interests between municipalities of equal standing has to be resolved.

Art. 65 KV/GR likewise guarantees municipal autonomy within the limits set by cantonal law. The municipalities of Graubünden are autonomous in broad areas of spatial planning and construction (Art. 3 para. 1 CRA; Art. 22 CRA concerning development). Superior law nevertheless remains reserved (Art. 22 para. 3 CRA), and Art. 45 para. 1 CRA limits the municipalities' margin. Under that provision, the General Development Plan determines at least the installations of basic and coarse-grained development and, where no subsequent planning has been specified, also the installations of fine-grained development that serve several parcels.

In the present case, this concerns an installation of fine-grained development, and no subsequent planning (site planning or quarter planning, Art. 26 para. 4 CRA) has been…