Facts

The company [A. SA] , active in general building contracting and registered in the Geneva commercial register on 19 September 2014, notified the Cantonal Employment Office (OCE) on 3 March 2017 of a loss of work due to bad weather between 10 and 27 January 2017, and applied for compensation.

By decision of 14 March 2017, confirmed on objection on 27 April 2017, the OCE refused weather-related compensation. It held that notice had been given 26 days late, so that the right to compensation, which could have begun on 10 January 2017, had to be postponed by 26 days, that is to 5 February 2017. The company having suffered no loss of work from that date, no compensation could be granted to it.

Seised of an appeal, the Social Insurance Chamber of the Court of Justice of the Republic and Canton of Geneva dismissed it by judgment of 30 August 2017.

The appellant company lodges a public law appeal with the Federal Supreme Court, seeking principally the award of weather-related compensation and, in the alternative, remittal of the matter to the cantonal authority. The OCE and the cantonal court seek dismissal of the appeal; the State Secretariat for Economic Affairs (SECO) waived submissions.

The dispute concerns the appellant's entitlement to weather-related compensation, the central question being whether the failure to observe the notice period may be sanctioned without excessive formalism and whether proof of the substantive conditions may still be adduced.

Considerations

The appeal is directed against a final decision given in public law matters by a cantonal court of last instance (arts. 90, 82 ff. and 86 para. 1 let. d FSCA). Filed within the prescribed time limit and in the required form, it is admissible. The Federal Supreme Court relies on the facts established by the prior authority (art. 105 para. 1 FSCA) and may depart from them only if they were established in a manifestly incorrect manner or in breach of the law (art. 105 para. 2 FSCA); it is for the appellant to demonstrate arbitrariness.

Under art. 69 para. 1 UIO, enacted pursuant to art. 45 para. 1 UIA, the employer must notify the cantonal authority of the loss of work due to bad weather, using the SECO form, no later than the fifth day of the following calendar month. Where notice is given late without valid reason, the start of the right to compensation is postponed accordingly (art. 69 para. 2 UIO). The lower judges found that notice was late by 26 days and that there was no valid excuse, and then postponed the start of the right to 5 February 2017, a date after the last day of interruption (27 January 2017). They further characterised the time limit as a formal condition, the non-observance of which causes the loss of the right to compensation even if the substantive conditions were met.

The appellant invokes a breach of the prohibition of excessive formalism (art. 29 para. 1 Cst.) and of the right to adduce evidence, a component of the right to be heard (art. 29 para. 2 Cst.), arguing that the time limit requirement is justified by no interest deserving protection and that it hinders proof of the substantive conditions.

The Federal Supreme Court recalls that excessive formalism, as an aspect of denial of justice, exists where the strict application of procedural rules is justified by no interest deserving protection, becomes an end in itself, unduly complicates the realisation of substantive law, or unacceptably impedes access to the courts. The right to adduce evidence, for its part, presupposes relevant evidence capable of influencing the decision.

In the present case, the lateness of the notice is established and…