Facts
The Municipality of the City of Solothurn, together with Regio Energie Solothurn (RES), a public-law undertaking of the city, prepared a "Development Plan District Heating 1st Stage (North and South Parts)". The plan provides, in large parts of the municipality outside the old town, for zones with a basic obligation to connect to the district heating line. The basis was the "Masterplan Energy 2009" of the Municipal Council of 19 January 2010.
The plan was publicly displayed from 21 November to 20 December 2013. Four objections (five objectors, including the appellants) were rejected by the Municipal Council on 1 July 2014. The Government Council of the Canton of Solothurn dismissed the appeal on 26 April 2016, approved the plan with the development regulations and granted it the effect of a building permit (§ 39 para. 4 PTA). The Administrative Court of the Canton of Solothurn dismissed the appeal by judgment of 15 March 2017.
The five appellants, owners or residents of properties within the perimeter, requested before the Federal Supreme Court the annulment of the judgment and the non-approval of the plan, alternatively remittal to the municipality or the Administrative Court. They essentially complained of procedural defects (inspection of files, right to be heard, guarantee of access to the courts, fair procedure, participation, bias) as well as violations of statutory and constitutional law. The municipality and the Government Council requested dismissal.
The subject matter of the dispute was solely the development plan with regulations. According to the Federal Supreme Court, the lower instances had in principle examined the complaints regarding the right to be heard.
Essential findings on the inspection of files: The appellants had previously themselves confirmed having received ten specific files. Inspection of files from parallel proceedings (supervisory complaint, permit proceedings for exceptional and ancillary permits, heat supply contract between the city and RES) was not granted; the concession contract was however handed over. Missing statements of RES and of the City Building Department were subsequently obtained in the proceedings before the Government Council.
Essential defect: The planning perimeter was discernible down to the individual plot, but not how it had been determined. The derivation from the Masterplan (heat density, pipe diameter, economic viability) was too general, so that the exercise of discretion could not be reviewed.
Building permit: Under § 5 para. 1 of the development regulations, the plan partly has the character of a building permit for lines on public roads; for lines outside such roads a separate procedure applies. The Administrative Court did not enter into the complaint concerning the construction of the lines (premature construction).
Considerations
Subject matter and admissibility: The appeal in public law matters against the final cantonal decision of last instance in the fields of spatial planning and energy law is admissible under Art. 82 ff., Art. 86 para. 1 lit. d and Art. 90 FSCA. The appellants have standing under Art. 89 para. 1 FSCA. The subject matter of the dispute is only the development plan with regulations, not the supervisory notice or any separate building permits.
Inspection of files and right to be heard (Art. 29 para. 2 Cst.): The right encompasses inspection of the files relevant to the decision. In their submission of 30 September 2014 the appellants themselves listed and confirmed the files. Inspection of files from parallel proceedings is not required. Preliminary examination reports and spatial planning reports were accessible; concrete indications of further relevant documents were lacking. The defects regarding the statements of RES and the City Building Department were cured in the proceedings before the Government Council.
Planning perimeter: The perimeter must be justifiable. The authorities indeed enjoy considerable planning discretion, which however must be exercised according to factual and objective criteria and must remain reviewable. The general derivation from the Masterplan is not sufficient; to that extent the appellants were denied the right to be heard.
Permits and guarantee of access to the courts (Art. 29a, Art. 30 Cst.): Insofar as the plan grants building permits under § 39 para. 4 PTA for lines on public road areas, these form part of the procedure. The appellants are therefore entitled to be heard and to inspect…