Facts
Parties and instances: The Swiss Federal Railways SBB AG (respondent) intended, as part of the 4th supplementary phase of the Zurich S-Bahn network, to introduce a new accelerated line S20 from Zurich to Stäfa with stops in Küsnacht, Meilen and Männedorf. To relieve line S7 and to enable the S20, the trains of the S16, which turn around at Herrliberg-Feldmeilen station, are to be able to be stabled elsewhere. For this purpose, the SBB plan a new turnaround track southeast of the station on the mountain side.
Proceedings before the Federal Office of Transport (BAV): On 3 June 2013 the BAV approved the project (construction of the turnaround track, relocation of the running track from Herrliberg-Feldmeilen to Meilen, two new underpasses, adaptation of a road underpass, renewal of superstructure and substructure). The project is upward-compatible with a later double-track expansion to Meilen. The costs were estimated at approximately CHF 35 million. The objections of the interest group [A.] (15 appellants, proceedings 1C_162/2015), of [B.C.] and [C.C.] , and of [D.] (proceedings 1C_164/2015) were dismissed subject to conditions, insofar as they were admissible.
Lower instance: The Federal Administrative Court, Division I, dismissed the appeals on 12 February 2015, insofar as they were admissible. It conducted an on-site inspection, as did the BAV. It waived a response.
Before the Federal Supreme Court: The appellants applied for the annulment of the judgment of the lower instance; appellants 2, in the alternative, applied for remittal or supplementation of the plan approval with conditions. The SBB and the BAV applied for dismissal. By presidential order of 4 September 2015, suspensive effect was granted to the appeals.
Subject matter of the dispute: The railway plan approval for the turnaround track and the adaptations of the railway installations, in particular the EIA obligation, noise protection (travel and stationary noise), the environmental precautionary principle (Art. 11 para. 2 EPA), equal distribution of burdens regarding overhead line masts, the temporary use of a parcel, and the regulation of costs and compensation.
Considerations
1. Joinder and on-site inspection The two appeals are directed against the same decision with largely identical complaints, which is why the proceedings are joined. The request for an on-site inspection before the Federal Supreme Court is rejected, as the local conditions are sufficiently clear from the project plans, the inspection records and the file.
2. Subject matter of the dispute and procedural complaints The inclusion of the project 'Schaltposten Meilen' in the assessment of non-ionising radiation is rejected, as it is not the subject of the present plan approval and its construction was decided separately (finding that the magnetic field would not be altered). No connection between the projects is apparent. The complaint of a violation of the right to be heard for failure to mention the submission on this issue is unfounded, as the lower instance was not required to address a point lying outside the subject matter of the dispute.
3. EIA obligation A new turnaround track does not constitute a new railway line within the meaning of No. 12.1 of the Annex to the EIAO. According to No. 12.2 of the Annex to the EIAO in conjunction with Art. 10a EPA and Art. 1 EIAO, an EIA obligation for other railway installations exists only if the cost estimate (excluding safety installations) exceeds CHF 40 million. The SBB determined, on the basis of the cost estimate of April 2013, expected costs of approximately CHF 27 million; even with a 10% margin of uncertainty the amount remains clearly below the threshold. A review of each cost item for plausibility is not required where the threshold is not nearly reached. The appellants did not show to what extent the costs would be manifestly incorrect, and did not seriously assert that the threshold would be exceeded. The complaint regarding the establishment of facts is unfounded.
4. Noise protection The travel noise of the passing trains (railway noise) does not exceed the planning values at the appellants' properties. The table in the plan approval shows emissions, not immissions at the properties; the findings of the lower instance are not manifestly incorrect. Accordingly, there is no entitlement to sound insulation measures (Art. 20 and 25 EPA). For the stationary noise of the parked trains (industrial and commercial noise), the lower instance relied on an EMPA study: planning values are met from approximately 120 m, and immission limit values from approximately 73 m. The properties are located at least 120 m away; in the case of [D.] 's parcel (115 m), the turnaround track is partly shielded by two further properties. A specific noise forecast was therefore not required. There is no violation of the right to be heard, as the stationary noise was already addressed in the plan approval procedure and the appellants were able to comment at the on-site inspection. The complaints are unfounded.
5. Precautionary principle and examination of alternatives According to Art. 11 para. 2 EPA, emissions must be limited as part of precautionary measures, irrespective of existing pollution, insofar as this is technically and operationally feasible and economically acceptable. Where the planning values are complied with, additional measures are only required if they achieve a substantial additional emission reduction at relatively low cost (BGE 127 II 306 consid. 8). Art. 11 para. 2 EPA only permits environmental optimisation, not an alternative re-planning, in particular not where significant new effects on third parties arise (BGE 124 II 517 consid. 5d). The case law cited by the appellants on comprehensive examination of alternatives concerns other constellations not falling under Art. 11 para. 2 EPA. The demands to waive the turnaround track, to extend the S16 or change the timetable, or to extend track 1 go beyond optimisation; waiving the S20 is not reasonable under the given circumstances, and the track extension would not be upward-compatible. The variants 'Bahnhof Meilen' and 'Harbis' require new projects with different timetables and alignments. The alternative proposed by Dr. [E.] did not have to be submitted to the SBB for comment, as no substantial additional emission reduction at low cost could be achieved. The variant 'Wendegleis Süd' is not equivalent according to the findings of the lower…