Facts
The appellant, a public limited company ([A. AG] ), is the owner of plot No. 342 in the municipality of Vinelz on Lake Biel. The plot is partly in the lake and includes a holiday home and a jetty extending about 20 m into the lake.
In 1990 the District Chief Engineer granted a water construction police permit for the expansion of the harbour and the renewal of the boat jetty to the same extent. The then owner later rammed six piles into the lake bed, which a neighbour objected to. In 1996 the Municipality of Vinelz ordered the new owner to restore the original state. The subsequent retroactive building application for 'erecting six rammed piles for mooring boats' led to several objections and remained pending for a long time. In the meantime the property changed ownership twice.
In 2012 the Office for Municipalities and Spatial Planning refused the exceptional permit for building outside the building zone. The Regional Governor's Office thereafter dismissed the building application and ordered the removal of the six piles. The Building, Transport and Energy Directorate (ACI) confirmed this in 2013. The Administrative Court of the Canton of Bern dismissed the administrative law appeal by judgment of 16 December 2014, insofar as it was admissible.
By public law appeal of 19 January 2015, the appellant requested the annulment of the judgment and the granting of the building permit. In the alternative, it requested remittal for an on-site inspection, in the further alternative an exceptional permit under Art. 24 ff. SPA, and in the further alternative waiver of the restoration. The ACI and the Administrative Court requested dismissal. The Federal Office for Spatial Development considered the judgment correct, and the Federal Office for the Environment considered the restoration unproblematic from an environmental law perspective.
The subject matter of the dispute is whether the six piles can be subsequently authorised and whether restoring the former state is proportionate.
Considerations
The appeal against the final cantonal decision in a public law matter (Art. 82 lit. a and Art. 86 para. 1 lit. d FSCA) is admissible, as the appellant is legitimised as the building applicant and the party obliged to restore (Art. 89 para. 1 FSCA). The complaints concerning the facts are unfounded: a manifestly incorrect finding of fact (Art. 97 para. 1 FSCA) was not substantiated, and the complaint of violation of the right to be heard due to the refused on-site inspection does not meet the requirements of reasoning (Art. 42 para. 2, Art. 106 para. 2 FSCA).
The complaint concerning the five-year time limit under Art. 46 para. 3 BauG is inadmissible, because the appellant does not engage with the reasoning of the lower court, according to which the time limit is not applicable at all due to a matter governed by federal law.
A claim to equal treatment in an unlawful situation (Art. 8 para. 1 Cst.) exists only where there is a consistent unlawful practice which the authority indicates it will continue to follow (BGE 136 I 65). As the appellant does not dispute the absence of a continued unlawful practice, a violation must be denied.
As regards the protection of existing rights, the Federal Supreme Court notes that former Art. 11 BauG constitutes a special provision which permits private construction projects in waters only on released water areas and does not provide for extensions. Departing from the lower court, Art. 41c para. 2 WPO is not independent within the scope of Art. 24c SPA, so that a moderate extension may also be permissible. Decisive, however, remains the balancing of interests under Art. 24c para. 5 SPA, or the examination of the important concerns of spatial planning, which is also required without applying Art. 24 SPA.
The lower court's balancing of interests is not open to objection. Pursuant to Art. 1 para. 2 lit. a, Art. 3 para. 2 lit. c…